Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete

Precoated/mill finish aluminium North light curves

Item number
12.66.3
Priced inputs
7
Derived rate
1,055.90 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.66.3 Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium North light curves — is derived from 7 priced inputs and works out to ₹1,055.90 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Details of North light curve 20.20 metres
  • long complete length
  • Length of ridges 20.2 metre + 5% wastage =
  • 1.01 metre. Total =23.11 metre.
CodeInputUnitQuantityRate (INR)Amount (INR)
3070Precoated/Mill finish Aluminium plain north light cuvesPrecoated/Mill finish Aluminium plain north light cuvesMaterialmetre23.11592.0013,681.12
3074Stainless steel self tapping screw of 6x50mm with SS hex cap and 3mm thick EPDM sealStainless steel self tapping screw of 6x50 mm with SS hex cap and 3 mm thick EPDM sealMaterial100 Nos0.4511.00204.40
9977Carriage of screws, washers and curvesMaterialL.S.9.882.2722.43
9999SundriesMaterialL.S.6.242.2714.16
0130MistryLabourday0.1897.0089.70
0112Carpenter 2nd classLabourday0.3816.00244.80
0114BeldarLabourday1736.00736.00
Total
14,992.61
Add 1 % Water charges on “W”
149.93
TOTAL
15,142.54
Add GST on “X” (multiplying factor 0.2127)
3,220.82
TOTAL
18,363.36
Add 15% CPOH on “Y”
2,754.50
TOTAL
21,117.86
Add Cess @ 1% on “Z”
211.18
Cost of 20.20 metre
21,329.04
Cost of 1 metre
1,055.89
Say
1,055.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 946. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.