Skip to main content
R/DAR 2023

Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete

Precoated/mill finish aluminium North light curves
Item number
12.66.3
Priced inputs
7
Derived rate
₹1,055.90/ METRE
D-01/RATE ANALYSISITEM 12.66.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.66.3 (Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium North light curves) is derived from 7 priced inputs and works out to ₹1,055.90 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Details of North light curve 20.20 metres
  • long complete length
  • Length of ridges 20.2 metre + 5% wastage =
  • 1.01 metre. Total =23.11 metre.
ANALYSIS OF RATES · ITEM 12.66.3
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3070MATPrecoated/Mill finish Aluminium plain north light cuvesPrecoated/Mill finish Aluminium plain north light cuvesmetre23.11592.0013,681.12
3074MATStainless steel self tapping screw of 6x50mm with SS hex cap and 3mm thick EPDM sealStainless steel self tapping screw of 6x50 mm with SS hex cap and 3 mm thick EPDM seal100 Nos0.4511.00204.40
9977MATCarriage of screws, washers and curvesL.S.9.882.2722.43
9999MATSundriesL.S.6.242.2714.16
0130LABMistryday0.1897.0089.70
0112LABCarpenter 2nd classday0.3816.00244.80
0114LABBeldarday1736.00736.00
BUILD-UP TO RATE
Total
14,992.61
Add 1 % Water charges on “W”
+149.93
TOTAL
15,142.54
Add GST on “X” (multiplying factor 0.2127)
+3,220.82
TOTAL
18,363.36
Add 15% CPOH on “Y”
+2,754.50
TOTAL
21,117.86
Add Cess @ 1% on “Z”
+211.18
Cost of 20.20 metre
21,329.04
Cost of 1 metre
1,055.89
SAY
₹1,055.90
D-02/SOURCEPRINTED PAGE 946
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
946

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 946. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.