Providing and fixing thermal insulation with Resin Bonded rock wool conforming to IS: 8183, having density 48 kg/m3, 50 mm thick,wrapped in 200 G Virgin Polythene Bags fixed to wall with screw, rawel plug & washers and held and in position by criss cossing GI wire etc. complete as per directions of Engineer-in-Charge

Item number
12.62
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹322.50/ SQM
D-01/RATE ANALYSISITEM 12.62

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.62 (Providing and fixing thermal insulation with Resin Bonded rock wool conforming to IS: 8183, having density 48 kg/m3, 50 mm thick,wrapped in 200 G Virgin Polythene Bags fixed to wall with screw, rawel plug & washers and held and in position by criss cossing GI wire etc. complete as per directions of Engineer-in-Charge) is derived from 5 priced inputs for 10 sqm and works out to ₹322.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Area for 10.00sqm. (Finished surface)=10.00sqm.+ Add 10% for ovelappings
  • &wastage= 1.00sqm. Total= 11.00sqm
ANALYSIS OF RATES · ITEM 12.62DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7273MATResin Bonded Rockwool 48 kg/m3sqm11117.001,287.00
9999MATSundries including GI wire 20 SWG and Virgin polythene bags 200 gram and CarriageL.S.522.27118.04
0111LABCarpenter 1st classday0.5897.00448.50
0114LABBeldarday0.5736.00368.00
9999MATSundries (screws & washers)L.S.202.2745.40
BUILD-UP TO RATE
TOTAL
2,266.94
Add 1 % Water charges on “W”
+22.67
TOTAL
2,289.61
Add GST on “X” (multiplying factor 0.2127)
+487.00
TOTAL
2,776.61
Add 15% CPOH on “Y”
+416.49
TOTAL
3,193.10
Add Cess @ 1% on “Z”
+31.93
Cost of 10 sqm
3,225.03
Cost of 1 sqm
322.50
SAY
₹322.50
D-02/SOURCEPRINTED PAGE 930
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
930

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 930. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.