Providing and fixing thermal insulation with Resin bonded rock wool conforming to IS: 8183, density 48 kg/m3, 50 mm thick, wrapped in 200 G virgin Polythene bags placed over existing false ceilng and held in position by criss-crossing Gl wire
- Item number
- 12.61
- Analysis basis
- 10 sqm
- Priced inputs
- 4
- Derived rate
- ₹316.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.61 (Providing and fixing thermal insulation with Resin bonded rock wool conforming to IS: 8183, density 48 kg/m3, 50 mm thick, wrapped in 200 G virgin Polythene bags placed over existing false ceilng and held in position by criss-crossing Gl wire) is derived from 4 priced inputs for 10 sqm and works out to ₹316.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Area for 10.00sqm. (Finished surface)=10.00sqm.+ Add 10% for ovelappings
- &wastage= 1.00sqm. Total= 11.00sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7273 | MAT | Resin Bonded Rockwool 48 kg/m3 | sqm | 11 | 117.00 | 1,287.00 |
| 9999 | MAT | Sundries including GI wire 20 SWG and polythene bags 200gms | L.S. | 52 | 2.27 | 118.04 |
| 0111 | LAB | Carpenter 1st class | day | 0.5 | 897.00 | 448.50 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
- TOTAL
- 2,221.54
- Add 1 % Water charges on “W”
- +22.22
- TOTAL
- 2,243.76
- Add GST on “X” (multiplying factor 0.2127)
- +477.25
- TOTAL
- 2,721.01
- Add 15% CPOH on “Y”
- +408.15
- TOTAL
- 3,129.16
- Add Cess @ 1% on “Z”
- +31.29
- Cost of 10 sqm
- 3,160.45
- Cost of 1 sqm
- 316.05
- SAY
- ₹316.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 930
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 930. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.