Skip to main content
R/DAR 2023

Providing and fixing thermal insulation with Resin bonded rock wool conforming to IS: 8183, density 48 kg/m3, 50 mm thick, wrapped in 200 G virgin Polythene bags placed over existing false ceilng and held in position by criss-crossing Gl wire

Item number
12.61
Analysis basis
10 sqm
Priced inputs
4
Derived rate
₹316.05/ SQM
D-01/RATE ANALYSISITEM 12.61

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.61 (Providing and fixing thermal insulation with Resin bonded rock wool conforming to IS: 8183, density 48 kg/m3, 50 mm thick, wrapped in 200 G virgin Polythene bags placed over existing false ceilng and held in position by criss-crossing Gl wire) is derived from 4 priced inputs for 10 sqm and works out to ₹316.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Area for 10.00sqm. (Finished surface)=10.00sqm.+ Add 10% for ovelappings
  • &wastage= 1.00sqm. Total= 11.00sqm
ANALYSIS OF RATES · ITEM 12.61DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7273MATResin Bonded Rockwool 48 kg/m3sqm11117.001,287.00
9999MATSundries including GI wire 20 SWG and polythene bags 200gmsL.S.522.27118.04
0111LABCarpenter 1st classday0.5897.00448.50
0114LABBeldarday0.5736.00368.00
BUILD-UP TO RATE
TOTAL
2,221.54
Add 1 % Water charges on “W”
+22.22
TOTAL
2,243.76
Add GST on “X” (multiplying factor 0.2127)
+477.25
TOTAL
2,721.01
Add 15% CPOH on “Y”
+408.15
TOTAL
3,129.16
Add Cess @ 1% on “Z”
+31.29
Cost of 10 sqm
3,160.45
Cost of 1 sqm
316.05
SAY
₹316.05
D-02/SOURCEPRINTED PAGE 930
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
930

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 930. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.