CPWD Analysis of Rates · Roofing

Providing and fixing thermal insulation of ceiling (under deck insulation) with Resin Bonded Rockwool conforming to IS: 8183,density 48 kg/m3, 50 mm thick, wrapped in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire mesh of 12.5mm x 24 gauge wire mesh, for top most ceiling of building

Item number
12.60
Analysis basis
Details of cost for 10 sqm
Priced inputs
5
Derived rate
667.05 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.60 Providing and fixing thermal insulation of ceiling (under deck insulation) with Resin Bonded Rockwool conforming to IS: 8183,density 48 kg/m3, 50 mm thick, wrapped in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire mesh of 12.5mm x 24 gauge wire mesh, for top most ceiling of building — is derived from 5 priced inputs for 10 sqm and works out to ₹667.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Area for 10.00 sqm.
  • (Finished surface)=10.00sqm.+ Add 10% for
  • ovelappings &wastage= 1.00sqm.
  • Total= 11.00sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
7273Resin Bonded Rockwool 48 kg/m3Materialsqm11117.001,287.00
9999Sundries including GI wire 20 SWG and polythene bags 200gmsMaterialL.S.1042.27236.08
9999GI chiken mesh 12.5mm x 24 SWGMaterialL.S.3512.27796.77
0111Carpenter 1st classLabourday1897.00897.00
0114BeldarLabourday2736.001,472.00
TOTAL
4,688.85
Add 1 % Water charges on “W”
46.89
TOTAL
4,735.74
Add GST on “X” (multiplying factor 0.2127)
1,007.29
TOTAL
5,743.03
Add 15% CPOH on “Y”
861.45
TOTAL
6,604.48
Add Cess @ 1% on “Z”
66.04
Cost of 10 sqm.
6,670.52
Cost of 1 sqm.
667.05
Say
667.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 929. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.