Providing and fixing thermal insulation of ceiling (under deck insulation) with Resin Bonded Rockwool conforming to IS: 8183,density 48 kg/m3, 50 mm thick, wrapped in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire mesh of 12.5mm x 24 gauge wire mesh, for top most ceiling of building
- Item number
- 12.60
- Analysis basis
- 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹667.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.60 (Providing and fixing thermal insulation of ceiling (under deck insulation) with Resin Bonded Rockwool conforming to IS: 8183,density 48 kg/m3, 50 mm thick, wrapped in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire mesh of 12.5mm x 24 gauge wire mesh, for top most ceiling of building) is derived from 5 priced inputs for 10 sqm and works out to ₹667.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Area for 10.00 sqm.
- (Finished surface)=10.00sqm.+ Add 10% for
- ovelappings &wastage= 1.00sqm.
- Total= 11.00sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7273 | MAT | Resin Bonded Rockwool 48 kg/m3 | sqm | 11 | 117.00 | 1,287.00 |
| 9999 | MAT | Sundries including GI wire 20 SWG and polythene bags 200gms | L.S. | 104 | 2.27 | 236.08 |
| 9999 | MAT | GI chiken mesh 12.5mm x 24 SWG | L.S. | 351 | 2.27 | 796.77 |
| 0111 | LAB | Carpenter 1st class | day | 1 | 897.00 | 897.00 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
- TOTAL
- 4,688.85
- Add 1 % Water charges on “W”
- +46.89
- TOTAL
- 4,735.74
- Add GST on “X” (multiplying factor 0.2127)
- +1,007.29
- TOTAL
- 5,743.03
- Add 15% CPOH on “Y”
- +861.45
- TOTAL
- 6,604.48
- Add Cess @ 1% on “Z”
- +66.04
- Cost of 10 sqm.
- 6,670.52
- Cost of 1 sqm.
- 667.05
- SAY
- ₹667.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 929
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 929. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.