Providing and fixing thermal insulation of ceiling (under deck insulation) with Resin Bonded Rockwool conforming to IS: 8183,density 48 kg/m3, 50 mm thick, wrapped in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire mesh of 12.5mm x 24 gauge wire mesh, for top most ceiling of building

Item number
12.60
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹667.05/ SQM
D-01/RATE ANALYSISITEM 12.60

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.60 (Providing and fixing thermal insulation of ceiling (under deck insulation) with Resin Bonded Rockwool conforming to IS: 8183,density 48 kg/m3, 50 mm thick, wrapped in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire mesh of 12.5mm x 24 gauge wire mesh, for top most ceiling of building) is derived from 5 priced inputs for 10 sqm and works out to ₹667.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Area for 10.00 sqm.
  • (Finished surface)=10.00sqm.+ Add 10% for
  • ovelappings &wastage= 1.00sqm.
  • Total= 11.00sqm
ANALYSIS OF RATES · ITEM 12.60DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7273MATResin Bonded Rockwool 48 kg/m3sqm11117.001,287.00
9999MATSundries including GI wire 20 SWG and polythene bags 200gmsL.S.1042.27236.08
9999MATGI chiken mesh 12.5mm x 24 SWGL.S.3512.27796.77
0111LABCarpenter 1st classday1897.00897.00
0114LABBeldarday2736.001,472.00
BUILD-UP TO RATE
TOTAL
4,688.85
Add 1 % Water charges on “W”
+46.89
TOTAL
4,735.74
Add GST on “X” (multiplying factor 0.2127)
+1,007.29
TOTAL
5,743.03
Add 15% CPOH on “Y”
+861.45
TOTAL
6,604.48
Add Cess @ 1% on “Z”
+66.04
Cost of 10 sqm.
6,670.52
Cost of 1 sqm.
667.05
SAY
₹667.05
D-02/SOURCEPRINTED PAGE 929
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
929

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 929. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.