Providing and applying two coats of High Albedo paint having minimum Solar Reflective Index (SRI) 108 (with solar reflectance & thermal emittance tested as per ASTMC 1549 and ASTMC 1371 respectively), VOC less than 10 cc/gm. The coating thickness and the methodology of application shall be strctly as per manufacturer’s specifications and as approved by Engineer-in-Charge. Surface preparation includes cleaning with metal wire brush to remove all dust, fungus etc., washing with water all complete. The contractor shall give guarantee for the perfomance of SRI and also the durabitity of coating, all complete as per direction of Engineer-in-Charge
- Item number
- 12.63
- Analysis basis
- 10 Sqm
- Priced inputs
- 5
- Derived rate
- ₹357.60/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.63 (Providing and applying two coats of High Albedo paint having minimum Solar Reflective Index (SRI) 108 (with solar reflectance & thermal emittance tested as per ASTMC 1549 and ASTMC 1371 respectively), VOC less than 10 cc/gm. The coating thickness and the methodology of application shall be strctly as per manufacturer’s specifications and as approved by Engineer-in-Charge. Surface preparation includes cleaning with metal wire brush to remove all dust, fungus etc., washing with water all complete. The contractor shall give guarantee for the perfomance of SRI and also the durabitity of coating, all complete as per direction of Engineer-in-Charge) is derived from 5 priced inputs for 10 Sqm and works out to ₹357.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIALS :
- LABOUR :
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7238 | MAT | High Albedo paint | kg | 7.17 | 228.00 | 1,634.76 |
| 9977 | MAT | Carriage of paint | L.S. | 4.53 | 2.27 | 10.28 |
| 0114 | LAB | Beldar (for cleanign the surface)Beldar | day | 0.54 | 736.00 | 397.44 |
| 0131 | LAB | Painter | day | 0.54 | 816.00 | 440.64 |
| 9999 | MAT | Sundries (Brushes & T&P etc. | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 2,513.81
- Add 1 % Water charges on “W”
- +25.14
- TOTAL
- 2,538.95
- Add GST on “X” (multiplying factor 0.2127)
- +540.03
- TOTAL
- 3,078.98
- Add 15% CPOH on “Y”
- +461.85
- TOTAL
- 3,540.83
- Add Cess @ 1% on “Z”
- +35.41
- Cost of 10 Sqm.
- 3,576.24
- Cost of 1 Sqm.
- 357.62
- SAY
- ₹357.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 931
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 931. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.