Providing and applying two coats of High Albedo paint having minimum Solar Reflective Index (SRI) 108 (with solar reflectance & thermal emittance tested as per ASTMC 1549 and ASTMC 1371 respectively), VOC less than 10 cc/gm. The coating thickness and the methodology of application shall be strctly as per manufacturer’s specifications and as approved by Engineer-in-Charge. Surface preparation includes cleaning with metal wire brush to remove all dust, fungus etc., washing with water all complete. The contractor shall give guarantee for the perfomance of SRI and also the durabitity of coating, all complete as per direction of Engineer-in-Charge

Item number
12.63
Analysis basis
10 Sqm
Priced inputs
5
Derived rate
₹357.60/ SQM
D-01/RATE ANALYSISITEM 12.63

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.63 (Providing and applying two coats of High Albedo paint having minimum Solar Reflective Index (SRI) 108 (with solar reflectance & thermal emittance tested as per ASTMC 1549 and ASTMC 1371 respectively), VOC less than 10 cc/gm. The coating thickness and the methodology of application shall be strctly as per manufacturer’s specifications and as approved by Engineer-in-Charge. Surface preparation includes cleaning with metal wire brush to remove all dust, fungus etc., washing with water all complete. The contractor shall give guarantee for the perfomance of SRI and also the durabitity of coating, all complete as per direction of Engineer-in-Charge) is derived from 5 priced inputs for 10 Sqm and works out to ₹357.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIALS :
  • LABOUR :
ANALYSIS OF RATES · ITEM 12.63DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7238MATHigh Albedo paintkg7.17228.001,634.76
9977MATCarriage of paintL.S.4.532.2710.28
0114LABBeldar (for cleanign the surface)Beldarday0.54736.00397.44
0131LABPainterday0.54816.00440.64
9999MATSundries (Brushes & T&P etc.L.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
2,513.81
Add 1 % Water charges on “W”
+25.14
TOTAL
2,538.95
Add GST on “X” (multiplying factor 0.2127)
+540.03
TOTAL
3,078.98
Add 15% CPOH on “Y”
+461.85
TOTAL
3,540.83
Add Cess @ 1% on “Z”
+35.41
Cost of 10 Sqm.
3,576.24
Cost of 1 Sqm.
357.62
SAY
₹357.60
D-02/SOURCEPRINTED PAGE 931
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
931

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 931. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.