Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete
- Item number
- 12.51.4
- Analysis basis
- 8.23 metre
- Priced inputs
- 9
- Derived rate
- ₹451.50/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.51.4 (Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : Barge board (Upto 300 mm)) is derived from 9 priced inputs for 8.23 metre and works out to ₹451.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Completed length of barge boards = 8.23 +
- 5% wastage = 8.64 metre
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8676 | MAT | Precoated galvanised steel barge boardPrecoated galvanised steel barge board (upto 300 mm ) | metre | 8.64 | 253.00 | 2,185.92 |
| 0222 | MAT | Seam bolts and nuts 6 mm dia and 25 mm long | 10 Nos | 0.5 | 11.00 | 5.50 |
| 1211 | MAT | G.I. plain washer for seam bolts | 100 Nos | 0.1 | 32.00 | 3.20 |
| 1208 | MAT | Bitumen washer | 100 Nos | 0.05 | 30.00 | 1.50 |
| 9977 | MAT | Carriage of barge boards, bolts, nuts and washers | L.S. | 9.36 | 2.27 | 21.25 |
| 9999 | MAT | Sundries | L.S. | 6.76 | 2.27 | 15.35 |
| 0130 | LAB | Mistry | day | 0.04 | 897.00 | 35.88 |
| 0112 | LAB | Carpenter 2nd class | day | 0.06 | 816.00 | 48.96 |
| 0114 | LAB | Beldar | day | 0.4 | 736.00 | 294.40 |
- TOTAL
- 2,611.96
- Add 1 % Water charges on “W”
- +26.12
- TOTAL
- 2,638.08
- Add GST on “X” (multiplying factor 0.2127)
- +561.12
- TOTAL
- 3,199.20
- Add 15% CPOH on “Y”
- +479.88
- TOTAL
- 3,679.08
- Add Cess @ 1% on “Z”
- +36.79
- Cost of 8.23 metre
- 3,715.87
- Cost of 1.00 metre
- 451.50
- SAY
- ₹451.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 915
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 915. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.