CPWD Analysis of Rates · Roofing

Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete

Barge board (Upto 300 mm)

Item number
12.51.4
Analysis basis
Details of cost for 8.23 metre
Priced inputs
9
Derived rate
451.50 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.51.4 Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : Barge board (Upto 300 mm) — is derived from 9 priced inputs for 8.23 metre and works out to ₹451.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Completed length of barge boards = 8.23 +
  • 5% wastage = 8.64 metre
CodeInputUnitQuantityRate (INR)Amount (INR)
8676Precoated galvanised steel barge boardPrecoated galvanised steel barge board (upto 300 mm )Materialmetre8.64253.002,185.92
0222Seam bolts and nuts 6 mm dia and 25 mm longMaterial10 Nos0.511.005.50
1211G.I. plain washer for seam boltsMaterial100 Nos0.132.003.20
1208Bitumen washerMaterial100 Nos0.0530.001.50
9977Carriage of barge boards, bolts, nuts and washersMaterialL.S.9.362.2721.25
9999SundriesMaterialL.S.6.762.2715.35
0130MistryLabourday0.04897.0035.88
0112Carpenter 2nd classLabourday0.06816.0048.96
0114BeldarLabourday0.4736.00294.40
TOTAL
2,611.96
Add 1 % Water charges on “W”
26.12
TOTAL
2,638.08
Add GST on “X” (multiplying factor 0.2127)
561.12
TOTAL
3,199.20
Add 15% CPOH on “Y”
479.88
TOTAL
3,679.08
Add Cess @ 1% on “Z”
36.79
Cost of 8.23 metre
3,715.87
Cost of 1.00 metre
451.50
Say
451.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 915. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.