CPWD Analysis of Rates · Roofing

Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete

Crimp curve

Item number
12.51.5
Priced inputs
9
Derived rate
496.75 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.51.5 Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : Crimp curve — is derived from 9 priced inputs and works out to ₹496.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Details of crimp curve 20.2 metre long
  • complete length, Area 20.20 x 1.06 =21.412
  • sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
8677Precoated galvanised steel crimp curveMaterialsqm22.483259.005,823.10
1023Galvanised steel J or L hooks 8 mm diaMaterial10 Nos4130.00520.00
1209G.I. plain washer thickMaterial100 Nos0.435.0014.00
1208Bitumen washerMaterial100 Nos0.430.0012.00
9977Carriage of hooks, nuts, washers and curvesMaterialL.S.9.882.2722.43
9999SundriesMaterialL.S.6.242.2714.16
0130MistryLabourday0.1897.0089.70
0112Carpenter 2nd classLabourday0.3816.00244.80
0114BeldarLabourday1736.00736.00
TOTAL
7,476.19
Add 1 % Water charges on “W”
74.76
TOTAL
7,550.95
Add GST on “X” (multiplying factor 0.2127)
1,606.09
TOTAL
9,157.04
Add 15% CPOH on “Y”
1,373.56
TOTAL
10,530.60
Add Cess @ 1% on “Z”
105.31
Cost of 21.412 sqm
10,635.91
Cost of 1.00 sqm
496.73
Say
496.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 915. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.