CPWD Analysis of Rates · Roofing
Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete
Crimp curve
- Item number
- 12.51.5
- Priced inputs
- 9
- Derived rate
- ₹496.75 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.51.5 — Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : Crimp curve — is derived from 9 priced inputs and works out to ₹496.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Details of crimp curve 20.2 metre long
- complete length, Area 20.20 x 1.06 =21.412
- sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8677 | Precoated galvanised steel crimp curveMaterial | sqm | 22.483 | 259.00 | 5,823.10 |
| 1023 | Galvanised steel J or L hooks 8 mm diaMaterial | 10 Nos | 4 | 130.00 | 520.00 |
| 1209 | G.I. plain washer thickMaterial | 100 Nos | 0.4 | 35.00 | 14.00 |
| 1208 | Bitumen washerMaterial | 100 Nos | 0.4 | 30.00 | 12.00 |
| 9977 | Carriage of hooks, nuts, washers and curvesMaterial | L.S. | 9.88 | 2.27 | 22.43 |
| 9999 | SundriesMaterial | L.S. | 6.24 | 2.27 | 14.16 |
| 0130 | MistryLabour | day | 0.1 | 897.00 | 89.70 |
| 0112 | Carpenter 2nd classLabour | day | 0.3 | 816.00 | 244.80 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
- TOTAL
- 7,476.19
- Add 1 % Water charges on “W”
- 74.76
- TOTAL
- 7,550.95
- Add GST on “X” (multiplying factor 0.2127)
- 1,606.09
- TOTAL
- 9,157.04
- Add 15% CPOH on “Y”
- 1,373.56
- TOTAL
- 10,530.60
- Add Cess @ 1% on “Z”
- 105.31
- Cost of 21.412 sqm
- 10,635.91
- Cost of 1.00 sqm
- 496.73
- Say
- 496.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 915. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.