CPWD Analysis of Rates · Roofing
Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete
North light curves
- Item number
- 12.51.3
- Priced inputs
- 9
- Derived rate
- ₹546.10 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.51.3 — Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : North light curves — is derived from 9 priced inputs and works out to ₹546.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Details of North light curve 20.20 metres
- long complete length
- 20.20 + 5% wastage = 23.11 metre
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8675 | Precoated galvanised steel north light curvesMaterial | metre | 23.11 | 264.00 | 6,101.04 |
| 1023 | Galvanised steel J or L hooks 8 mm diaMaterial | 10 Nos | 4 | 130.00 | 520.00 |
| 1209 | G.I. plain washer thickMaterial | 100 Nos | 0.4 | 35.00 | 14.00 |
| 1208 | Bitumen washerMaterial | 100 Nos | 0.4 | 30.00 | 12.00 |
| 9977 | Carriage of hooks, nuts, washers and curvesMaterial | L.S. | 9.88 | 2.27 | 22.43 |
| 9999 | SundriesMaterial | L.S. | 6.24 | 2.27 | 14.16 |
| 0130 | MistryLabour | day | 0.1 | 897.00 | 89.70 |
| 0112 | Carpenter 2nd classLabour | day | 0.3 | 816.00 | 244.80 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
- TOTAL
- 7,754.13
- Add 1 % Water charges on “W”
- 77.54
- TOTAL
- 7,831.67
- Add GST on “X” (multiplying factor 0.2127)
- 1,665.80
- TOTAL
- 9,497.47
- Add 15% CPOH on “Y”
- 1,424.62
- TOTAL
- 10,922.09
- Add Cess @ 1% on “Z”
- 109.22
- Cost of 20.20 metre
- 11,031.31
- Cost of 1.00 metre
- 546.10
- Say
- 546.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 914. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works