Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete

North light curves

Item number
12.51.3
Priced inputs
9
Derived rate
546.10 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.51.3 Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : North light curves — is derived from 9 priced inputs and works out to ₹546.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Details of North light curve 20.20 metres
  • long complete length
  • 20.20 + 5% wastage = 23.11 metre
CodeInputUnitQuantityRate (INR)Amount (INR)
8675Precoated galvanised steel north light curvesMaterialmetre23.11264.006,101.04
1023Galvanised steel J or L hooks 8 mm diaMaterial10 Nos4130.00520.00
1209G.I. plain washer thickMaterial100 Nos0.435.0014.00
1208Bitumen washerMaterial100 Nos0.430.0012.00
9977Carriage of hooks, nuts, washers and curvesMaterialL.S.9.882.2722.43
9999SundriesMaterialL.S.6.242.2714.16
0130MistryLabourday0.1897.0089.70
0112Carpenter 2nd classLabourday0.3816.00244.80
0114BeldarLabourday1736.00736.00
TOTAL
7,754.13
Add 1 % Water charges on “W”
77.54
TOTAL
7,831.67
Add GST on “X” (multiplying factor 0.2127)
1,665.80
TOTAL
9,497.47
Add 15% CPOH on “Y”
1,424.62
TOTAL
10,922.09
Add Cess @ 1% on “Z”
109.22
Cost of 20.20 metre
11,031.31
Cost of 1.00 metre
546.10
Say
546.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 914. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works