Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete

Flashings/ Aprons.( Upto 600 mm)

Item number
12.51.2
Priced inputs
6
Derived rate
485.60 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.51.2 Providing and fixing precoated galvanised steel sheet roofing accessories of total coated thickness 0.50mm (base metal of minimum 0.45mm thickness with total coating thickness of 0.05mm) with Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : Flashings/ Aprons.( Upto 600 mm) — is derived from 6 priced inputs and works out to ₹485.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Details for shed of 20.2 metres completed
  • length
  • 20.20 + 5% wastage = 23.11 metre
CodeInputUnitQuantityRate (INR)Amount (INR)
8673Precoated galvanised steel flashings/aprons 0.50mm TCT and wide upto 600 mmPrecoated galvanised steel flashings/aprons 0.50 mm TCT and upto 600 mm wideMaterialmetre23.11259.005,985.49
9977Carriage of appron pieces. (The appron pieces are to be fixed with the same hooks as the sheets)MaterialL.S.3.252.277.38
9999SundriesMaterialL.S.3.252.277.38
0130MistryLabourday0.07897.0062.79
0112Carpenter 2nd classLabourday0.28816.00228.48
0114BeldarLabourday0.82736.00603.52
TOTAL
6,895.04
Add 1 % Water charges on “W”
68.95
TOTAL
6,963.99
Add GST on “X” (multiplying factor 0.2127)
1,481.24
TOTAL
8,445.23
Add 15% CPOH on “Y”
1,266.78
TOTAL
9,712.01
Add Cess @ 1% on “Z”
97.12
Cost of 20.20 metre
9,809.13
Cost of 1.00 metre
485.60
Say
485.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 914. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.