CPWD Analysis of Rates · Roofing
Providing and fixing unplasticised -PVC pipe clips of approved design to unplasticised - PVC rain water pipes by means of 50x50x50 mm hard wood plugs, screwed with M.S. screws of required length, including cutting brick work and fixing in cement mortar 1:4 (1 cement : 4 coarse sand) and making good the wall etc. complete
110 mm
- Item number
- 12.43.2
- Analysis basis
- Details of cost for 5 nos.
- Priced inputs
- 9
- Derived rate
- ₹371.30 / No
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.43.2 — Providing and fixing unplasticised -PVC pipe clips of approved design to unplasticised - PVC rain water pipes by means of 50x50x50 mm hard wood plugs, screwed with M.S. screws of required length, including cutting brick work and fixing in cement mortar 1:4 (1 cement : 4 coarse sand) and making good the wall etc. complete 110 mm — is derived from 9 priced inputs for 5 nos and works out to ₹371.30 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7215 | UPVC pipe clip 110 mmMaterial | each | 5 | 16.00 | 80.00 |
| 9977 | Carriage of U-PVC pipe clipsMaterial | L.S. | 2.47 | 2.27 | 5.61 |
| 0870 | PlugMaterial | each | 10 | 10.00 | 100.00 |
| 0116 | Fitter (grade 1)Labour | day | 0.125 | 897.00 | 112.13 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.75 | 816.00 | 612.00 |
| 0114 | BeldarLabour | day | 0.5 | 736.00 | 368.00 |
| 9999 | SundriesMaterial | L.S. | 7.15 | 2.27 | 16.23 |
| 9999 | SundriesMaterial | L.S. | 0.91 | 2.27 | 2.07 |
| 9999 | Sundries cement mortar 1:4 (1Cement : 4 Coarse sand)Material | L.S. | 3.9 | 2.27 | 8.85 |
- TOTAL
- 1,304.89
- Add 1 % Water charges on “W”
- 13.05
- TOTAL
- 1,317.94
- Add GST on “X” (multiplying factor 0.2127)
- 280.33
- TOTAL
- 1,598.27
- Add 15% CPOH on “Y”
- 239.74
- TOTAL
- 1,838.01
- Add Cess @ 1% on “Z”
- 18.38
- Cost of 5 Nos.
- 1,856.39
- Cost of 1 No.
- 371.28
- Say
- 371.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 904. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.