Skip to main content

CPWD Analysis of Rates · Roofing

Providing and fixing unplasticised -PVC pipe clips of approved design to unplasticised - PVC rain water pipes by means of 50x50x50 mm hard wood plugs, screwed with M.S. screws of required length, including cutting brick work and fixing in cement mortar 1:4 (1 cement : 4 coarse sand) and making good the wall etc. complete

110 mm

Item number
12.43.2
Analysis basis
Details of cost for 5 nos.
Priced inputs
9
Derived rate
371.30 / No

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.43.2 Providing and fixing unplasticised -PVC pipe clips of approved design to unplasticised - PVC rain water pipes by means of 50x50x50 mm hard wood plugs, screwed with M.S. screws of required length, including cutting brick work and fixing in cement mortar 1:4 (1 cement : 4 coarse sand) and making good the wall etc. complete 110 mm — is derived from 9 priced inputs for 5 nos and works out to ₹371.30 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7215UPVC pipe clip 110 mmMaterialeach516.0080.00
9977Carriage of U-PVC pipe clipsMaterialL.S.2.472.275.61
0870PlugMaterialeach1010.00100.00
0116Fitter (grade 1)Labourday0.125897.00112.13
0124Mason 2nd classMason 2nd classLabourday0.75816.00612.00
0114BeldarLabourday0.5736.00368.00
9999SundriesMaterialL.S.7.152.2716.23
9999SundriesMaterialL.S.0.912.272.07
9999Sundries cement mortar 1:4 (1Cement : 4 Coarse sand)MaterialL.S.3.92.278.85
TOTAL
1,304.89
Add 1 % Water charges on “W”
13.05
TOTAL
1,317.94
Add GST on “X” (multiplying factor 0.2127)
280.33
TOTAL
1,598.27
Add 15% CPOH on “Y”
239.74
TOTAL
1,838.01
Add Cess @ 1% on “Z”
18.38
Cost of 5 Nos.
1,856.39
Cost of 1 No.
371.28
Say
371.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 904. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works