R/DAR 2023

Providing and fixing unplasticised -PVC pipe clips of approved design to unplasticised - PVC rain water pipes by means of 50x50x50 mm hard wood plugs, screwed with M.S. screws of required length, including cutting brick work and fixing in cement mortar 1:4 (1 cement : 4 coarse sand) and making good the wall etc. complete

75 mm
Item number
12.43.1
Analysis basis
5 nos
Priced inputs
9
Derived rate
₹369.85/ NO
D-01/RATE ANALYSISITEM 12.43.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.43.1 (Providing and fixing unplasticised -PVC pipe clips of approved design to unplasticised - PVC rain water pipes by means of 50x50x50 mm hard wood plugs, screwed with M.S. screws of required length, including cutting brick work and fixing in cement mortar 1:4 (1 cement : 4 coarse sand) and making good the wall etc. complete 75 mm) is derived from 9 priced inputs for 5 nos and works out to ₹369.85 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.43.1DETAILS OF COST FOR 5 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7214MATUPVC pipe clip 75 mmeach515.0075.00
9977MATCarriage of U-PVC pipe clipsL.S.2.472.275.61
0870MATPlugeach1010.00100.00
0116LABFitter (grade 1)day0.125897.00112.13
0124LABMason 2nd classMason 2nd classday0.75816.00612.00
0114LABBeldarday0.5736.00368.00
9999MATSundriesL.S.7.152.2716.23
9999MATSundriesL.S.0.912.272.07
9999MATSundries cement mortar 1:4 (1Cement : 4 Coarse sand)L.S.3.92.278.85
BUILD-UP TO RATE
TOTAL
1,299.89
Add 1 % Water charges on “W”
+13.00
TOTAL
1,312.89
Add GST on “X” (multiplying factor 0.2127)
+279.25
TOTAL
1,592.14
Add 15% CPOH on “Y”
+238.82
TOTAL
1,830.96
Add Cess @ 1% on “Z”
+18.31
Cost of 5 Nos.
1,849.27
Cost of 1 No.
369.85
SAY
₹369.85
D-02/SOURCEPRINTED PAGE 903
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
903

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 903. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.