CPWD Analysis of Rates · Roofing
Providing and fixing to the inlet mouth of rain water pipe cast iron grating 15 cm diameter and weighing not less than 440 grams
- Item number
- 12.44
- Analysis basis
- Details of cost for 1 grating
- Priced inputs
- 2
- Derived rate
- ₹54.70 / grating
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.44 — Providing and fixing to the inlet mouth of rain water pipe cast iron grating 15 cm diameter and weighing not less than 440 grams — is derived from 2 priced inputs for 1 grating and works out to ₹54.70 per grating after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7187 | C.I. grating 150 mm dia. (Weighing not less than 440 gm)C.I. grating 150 mm dia, weighing not less than 440 gmMaterial | each | 1 | 29.00 | 29.00 |
| 9977 | Carriage of material and fixing chargesMaterial | L.S. | 4.16 | 2.27 | 9.44 |
- TOTAL
- 38.44
- Add 1 % Water charges on “W”
- 0.38
- TOTAL
- 38.82
- Add GST on “X” (multiplying factor 0.2127)
- 8.26
- TOTAL
- 47.08
- Add 15% CPOH on “Y”
- 7.06
- TOTAL
- 54.14
- Add Cess @ 1% on “Z”
- 0.54
- Cost of each grating
- 54.68
- Say
- 54.70
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 904. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.