Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Bend 87.5°
- Item number
- 12.42.5.2
- Analysis basis
- 1 bend
- Priced inputs
- 4
- Derived rate
- ₹150.35/ BEND
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.5.2 (Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Bend 87.5° 110 mm bend) is derived from 4 priced inputs for 1 bend and works out to ₹150.35 per bend after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7209 | MAT | UPVC bend 87.5° 110 mm bend | each | 1 | 63.00 | 63.00 |
| 7191 | MAT | U-PVC pipes (working pressure 4 kg /sqcm) Rubber (Seal) Ring 110 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 110 mm dia | each | 1 | 12.00 | 12.00 |
| 9999 | MAT | Adhesive, and sundries etc. | L.S. | 2.73 | 2.27 | 6.20 |
| 9988 | MAT | Carriage and fixing charges | L.S. | 10.79 | 2.27 | 24.49 |
- TOTAL
- 105.69
- Add 1 % Water charges on “W”
- +1.06
- TOTAL
- 106.75
- Add GST on “X” (multiplying factor 0.2127)
- +22.71
- TOTAL
- 129.46
- Add 15% CPOH on “Y”
- +19.42
- TOTAL
- 148.88
- Add Cess @ 1% on “Z”
- +1.49
- Cost of 1 bend
- 150.37
- SAY
- ₹150.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 902
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 902. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.