Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Bend 87.5°

110 mm bend

Item number
12.42.5.2
Analysis basis
Details of cost for 1 bend
Priced inputs
4
Derived rate
150.35 / bend

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.5.2 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Bend 87.5° 110 mm bend — is derived from 4 priced inputs for 1 bend and works out to ₹150.35 per bend after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7209UPVC bend 87.5° 110 mm bendMaterialeach163.0063.00
7191U-PVC pipes (working pressure 4 kg /sqcm) Rubber (Seal) Ring 110 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 110 mm diaMaterialeach112.0012.00
9999Adhesive, and sundries etc.MaterialL.S.2.732.276.20
9988Carriage and fixing chargesMaterialL.S.10.792.2724.49
TOTAL
105.69
Add 1 % Water charges on “W”
1.06
TOTAL
106.75
Add GST on “X” (multiplying factor 0.2127)
22.71
TOTAL
129.46
Add 15% CPOH on “Y”
19.42
TOTAL
148.88
Add Cess @ 1% on “Z”
1.49
Cost of 1 bend
150.37
Say
150.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 902. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works