Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Bend 87.5°
110 mm bend
- Item number
- 12.42.5.2
- Analysis basis
- Details of cost for 1 bend
- Priced inputs
- 4
- Derived rate
- ₹150.35 / bend
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.5.2 — Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Bend 87.5° 110 mm bend — is derived from 4 priced inputs for 1 bend and works out to ₹150.35 per bend after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7209 | UPVC bend 87.5° 110 mm bendMaterial | each | 1 | 63.00 | 63.00 |
| 7191 | U-PVC pipes (working pressure 4 kg /sqcm) Rubber (Seal) Ring 110 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 110 mm diaMaterial | each | 1 | 12.00 | 12.00 |
| 9999 | Adhesive, and sundries etc.Material | L.S. | 2.73 | 2.27 | 6.20 |
| 9988 | Carriage and fixing chargesMaterial | L.S. | 10.79 | 2.27 | 24.49 |
- TOTAL
- 105.69
- Add 1 % Water charges on “W”
- 1.06
- TOTAL
- 106.75
- Add GST on “X” (multiplying factor 0.2127)
- 22.71
- TOTAL
- 129.46
- Add 15% CPOH on “Y”
- 19.42
- TOTAL
- 148.88
- Add Cess @ 1% on “Z”
- 1.49
- Cost of 1 bend
- 150.37
- Say
- 150.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 902. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.