Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Shoe (Plain)
- Item number
- 12.42.6.1
- Analysis basis
- 1 shoe
- Priced inputs
- 4
- Derived rate
- ₹93.10/ SHOE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.6.1 (Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Shoe (Plain) 75 mm Shoe) is derived from 4 priced inputs for 1 shoe and works out to ₹93.10 per shoe after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7212 | MAT | UPVC plain shoe 75 mm | each | 1 | 29.00 | 29.00 |
| 7190 | MAT | U-PVC pipes (working pressure 4 kg / sqcm) Rubber (Seal) Ring 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 75 mm dia | each | 1 | 9.00 | 9.00 |
| 9999 | MAT | Adhesive, and sundries etc. | L.S. | 2.73 | 2.27 | 6.20 |
| 9988 | MAT | Carriage and fixing charges | L.S. | 9.36 | 2.27 | 21.25 |
- TOTAL
- 65.45
- Add 1 % Water charges on “W”
- +0.65
- TOTAL
- 66.10
- Add GST on “X” (multiplying factor 0.2127)
- +14.06
- TOTAL
- 80.16
- Add 15% CPOH on “Y”
- +12.02
- TOTAL
- 92.18
- Add Cess @ 1% on “Z”
- +0.92
- Cost of 1 shoe
- 93.10
- SAY
- ₹93.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 902
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 902. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.