Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Bend 87.5°

75 mm bend
Item number
12.42.5.1
Analysis basis
1 bend
Priced inputs
4
Derived rate
₹105.90/ BEND
D-01/RATE ANALYSISITEM 12.42.5.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.5.1 (Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Bend 87.5° 75 mm bend) is derived from 4 priced inputs for 1 bend and works out to ₹105.90 per bend after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.42.5.1DETAILS OF COST FOR 1 BEND
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7208MATUPVC bend 87.5° 75 mm bendeach138.0038.00
7190MATU-PVC pipes (working pressure 4 kg / sqcm) Rubber (Seal) Ring 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 75 mm diaeach19.009.00
9999MATAdhesive, and sundries etc.L.S.2.732.276.20
9988MATCarriage and fixing chargesL.S.9.362.2721.25
BUILD-UP TO RATE
TOTAL
74.45
Add 1 % Water charges on “W”
+0.74
TOTAL
75.19
Add GST on “X” (multiplying factor 0.2127)
+15.99
TOTAL
91.18
Add 15% CPOH on “Y”
+13.68
TOTAL
104.86
Add Cess @ 1% on “Z”
+1.05
Cost of 1 bend
105.91
SAY
₹105.90
D-02/SOURCEPRINTED PAGE 901
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
901

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 901. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.