Skip to main content
R/DAR 2023

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Single tee with door

75x75x75 mm
Item number
12.42.3.1
Analysis basis
1 tee
Priced inputs
3
Derived rate
₹164.20/ TEE
D-01/RATE ANALYSISITEM 12.42.3.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.3.1 (Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Single tee with door 75x75x75 mm) is derived from 3 priced inputs for 1 tee and works out to ₹164.20 per tee after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.42.3.1DETAILS OF COST FOR 1 TEE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7198MATUPVC single equal Tee (with door) 75x75x75 mmeach164.0064.00
7190MATU-PVC pipes (working pressure 4 kg /sqcm) Rubber (Seal) Ring 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 75 mm diaeach39.0027.00
9988MATAdhesive, Carriage of material rubber washer etc. including fixing chargesL.S.10.762.2724.43
BUILD-UP TO RATE
TOTAL
115.43
Add 1 % Water charges on “W”
+1.15
TOTAL
116.58
Add GST on “X” (multiplying factor 0.2127)
+24.80
TOTAL
141.38
Add 15% CPOH on “Y”
+21.21
TOTAL
162.59
Add Cess @ 1% on “Z”
+1.63
Cost of 1 tee
164.22
SAY
₹164.20
D-02/SOURCEPRINTED PAGE 900
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
900

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 900. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.