Skip to main content
R/DAR 2023

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Single pushfit Coupler

110 mm
Item number
12.42.2.2
Analysis basis
1 coupler
Priced inputs
4
Derived rate
₹127.60/ COUPLER
D-01/RATE ANALYSISITEM 12.42.2.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.2.2 (Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Single pushfit Coupler 110 mm) is derived from 4 priced inputs for 1 coupler and works out to ₹127.60 per coupler after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.42.2.2DETAILS OF COST FOR 1 COUPLER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7195MATUPVC pushfit coupler (single) 110 mm thickeach135.0035.00
7191MATU-PVC pipes (working pressure 4 kg /sq.cm) Rubber (Seal) Ring 110 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 110 mm diaeach212.0024.00
9999MATAdhesive, and sundries etc.L.S.2.732.276.20
9988MATCarriage and fixing chargesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
89.69
Add 1 % Water charges on “W”
+0.90
TOTAL
90.59
Add GST on “X” (multiplying factor 0.2127)
+19.27
TOTAL
109.86
Add 15% CPOH on “Y”
+16.48
TOTAL
126.34
Add Cess @ 1% on “Z”
+1.26
Cost of 1 coupler
127.60
SAY
₹127.60
D-02/SOURCEPRINTED PAGE 899
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
899

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 899. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.