Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Single pushfit Coupler
- Item number
- 12.42.2.2
- Analysis basis
- 1 coupler
- Priced inputs
- 4
- Derived rate
- ₹127.60/ COUPLER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.2.2 (Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Single pushfit Coupler 110 mm) is derived from 4 priced inputs for 1 coupler and works out to ₹127.60 per coupler after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7195 | MAT | UPVC pushfit coupler (single) 110 mm thick | each | 1 | 35.00 | 35.00 |
| 7191 | MAT | U-PVC pipes (working pressure 4 kg /sq.cm) Rubber (Seal) Ring 110 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 110 mm dia | each | 2 | 12.00 | 24.00 |
| 9999 | MAT | Adhesive, and sundries etc. | L.S. | 2.73 | 2.27 | 6.20 |
| 9988 | MAT | Carriage and fixing charges | L.S. | 10.79 | 2.27 | 24.49 |
- TOTAL
- 89.69
- Add 1 % Water charges on “W”
- +0.90
- TOTAL
- 90.59
- Add GST on “X” (multiplying factor 0.2127)
- +19.27
- TOTAL
- 109.86
- Add 15% CPOH on “Y”
- +16.48
- TOTAL
- 126.34
- Add Cess @ 1% on “Z”
- +1.26
- Cost of 1 coupler
- 127.60
- SAY
- ₹127.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 899
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 899. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.