CPWD Analysis of Rates · Roofing
Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Single pushfit Coupler
75 mm
- Item number
- 12.42.2.1
- Analysis basis
- Details of cost for 1 coupler
- Priced inputs
- 4
- Derived rate
- ₹93.10 / coupler
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.2.1 — Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Single pushfit Coupler 75 mm — is derived from 4 priced inputs for 1 coupler and works out to ₹93.10 per coupler after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7194 | UPVC pushfit coupler (single) 75 mm thickMaterial | each | 1 | 20.00 | 20.00 |
| 7190 | U-PVC pipes (working pressure 4 kg /sqcm.) Rubber (Seal) Ring 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 75 mm diaMaterial | each | 2 | 9.00 | 18.00 |
| 9999 | Adhesive, and sundries etc.Material | L.S. | 2.73 | 2.27 | 6.20 |
| 9988 | Carriage and fixing chargesMaterial | L.S. | 9.36 | 2.27 | 21.25 |
- TOTAL
- 65.45
- Add 1 % Water charges on “W”
- 0.65
- TOTAL
- 66.10
- Add GST on “X” (multiplying factor 0.2127)
- 14.06
- TOTAL
- 80.16
- Add 15% CPOH on “Y”
- 12.02
- TOTAL
- 92.18
- Add Cess @ 1% on “Z”
- 0.92
- Cost of 1 coupler
- 93.10
- Say
- 93.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 899. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works