Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Coupler

110 mm
Item number
12.42.1.2
Analysis basis
1 coupler
Priced inputs
4
Derived rate
₹136.15/ COUPLER
D-01/RATE ANALYSISITEM 12.42.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.1.2 (Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Coupler 110 mm) is derived from 4 priced inputs for 1 coupler and works out to ₹136.15 per coupler after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.42.1.2DETAILS OF COST FOR 1 COUPLER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7193MATUPVC coupler for UPVC drainage pipes 110 mmeach141.0041.00
7191MATU-PVC pipes (working pressure 4 kg /sqcm) Rubber (Seal) Ring 110 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 110 mm diaeach212.0024.00
9999MATAdhesive, and sundries etc.L.S.2.732.276.20
9988MATCarriage and fixing chargesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
95.69
Add 1 % Water charges on “W”
+0.96
TOTAL
96.65
Add GST on “X” (multiplying factor 0.2127)
+20.56
TOTAL
117.21
Add 15% CPOH on “Y”
+17.58
TOTAL
134.79
Add Cess @ 1% on “Z”
+1.35
Cost of 1 coupler
136.14
SAY
₹136.15
D-02/SOURCEPRINTED PAGE 899
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
899

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 899. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.