Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Coupler
- Item number
- 12.42.1.1
- Analysis basis
- 1 coupler
- Priced inputs
- 4
- Derived rate
- ₹91.70/ COUPLER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.1.1 (Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Coupler 75 mm) is derived from 4 priced inputs for 1 coupler and works out to ₹91.70 per coupler after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7192 | MAT | UPVC coupler for UPVC drainage pipes 75 mm | each | 1 | 19.00 | 19.00 |
| 7190 | MAT | U-PVC pipes (working pressure 4 kg /sqcm.) Rubber (Seal) Ring 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 75 mm dia | each | 2 | 9.00 | 18.00 |
| 9999 | MAT | Adhesive, and sundries etc. | L.S. | 2.73 | 2.27 | 6.20 |
| 9988 | MAT | Carriage and fixing charges | L.S. | 9.36 | 2.27 | 21.25 |
- TOTAL
- 64.45
- Add 1 % Water charges on “W”
- +0.64
- TOTAL
- 65.09
- Add GST on “X” (multiplying factor 0.2127)
- +13.84
- TOTAL
- 78.93
- Add 15% CPOH on “Y”
- +11.84
- TOTAL
- 90.77
- Add Cess @ 1% on “Z”
- +0.91
- Cost of 1 coupler
- 91.68
- SAY
- ₹91.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 898
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 898. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.