R/DAR 2023

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Coupler

75 mm
Item number
12.42.1.1
Analysis basis
1 coupler
Priced inputs
4
Derived rate
₹91.70/ COUPLER
D-01/RATE ANALYSISITEM 12.42.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.42.1.1 (Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion Coupler 75 mm) is derived from 4 priced inputs for 1 coupler and works out to ₹91.70 per coupler after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.42.1.1DETAILS OF COST FOR 1 COUPLER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7192MATUPVC coupler for UPVC drainage pipes 75 mmeach119.0019.00
7190MATU-PVC pipes (working pressure 4 kg /sqcm.) Rubber (Seal) Ring 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 75 mm diaeach29.0018.00
9999MATAdhesive, and sundries etc.L.S.2.732.276.20
9988MATCarriage and fixing chargesL.S.9.362.2721.25
BUILD-UP TO RATE
TOTAL
64.45
Add 1 % Water charges on “W”
+0.64
TOTAL
65.09
Add GST on “X” (multiplying factor 0.2127)
+13.84
TOTAL
78.93
Add 15% CPOH on “Y”
+11.84
TOTAL
90.77
Add Cess @ 1% on “Z”
+0.91
Cost of 1 coupler
91.68
SAY
₹91.70
D-02/SOURCEPRINTED PAGE 898
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
898

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 898. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.