CPWD Analysis of Rates · Roofing
Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes
110 mm diameter
- Item number
- 12.41.2
- Analysis basis
- Details of cost for 6.00 metres
- Priced inputs
- 8
- Derived rate
- ₹377.40 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.41.2 — Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes 110 mm diameter — is derived from 8 priced inputs for 6.00 metres and works out to ₹377.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7189 | U-PVC pipes (working pressure 4 kg / sqcm) Single socketed pipe 110 mm diaU-PVC pipes (working pressure 4 kg / cm²) Single socketed pipe 110 mm diaMaterial | metre | 6 | 142.00 | 852.00 |
| 7191 | U-PVC pipes (working pressure 4 kg / sqcm.) Rubber (Seal) Ring 110 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 110 mm diaMaterial | each | 1 | 12.00 | 12.00 |
| 9977 | Carriage of materialsMaterial | L.S. | 17.55 | 2.27 | 39.84 |
| 9999 | Adhesive, and sundries etc.Material | L.S. | 8.06 | 2.27 | 18.30 |
| 0116 | Fitter (grade 1)Labour | day | 0.23 | 897.00 | 206.31 |
| 0114 | BeldarLabour | day | 0.45 | 736.00 | 331.20 |
| 0100 | BandhaniLabour | day | 0.11 | 816.00 | 89.76 |
| 9999 | Scaffolding etc.Material | L.S. | 18.59 | 2.27 | 42.20 |
- TOTAL
- 1,591.61
- Add 1 % Water charges on “W”
- 15.92
- TOTAL
- 1,607.53
- Add GST on “X” (multiplying factor 0.2127)
- 341.92
- TOTAL
- 1,949.45
- Add 15% CPOH on “Y”
- 292.42
- TOTAL
- 2,241.87
- Add Cess @ 1% on “Z”
- 22.42
- Cost of 6.00 metre
- 2,264.29
- Cost of 1.00 metre
- 377.38
- Say
- 377.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 898. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.