Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes

75 mm diameter

Item number
12.41.1
Analysis basis
Details of cost for 6.00 metres
Priced inputs
8
Derived rate
248.80 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.41.1 Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes 75 mm diameter — is derived from 8 priced inputs for 6.00 metres and works out to ₹248.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7188U-PVC pipes (working pressure 4 kg / sqcm.) Single socketed pipe 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Single socketed pipe 75 mm diaMaterialmetre674.00444.00
7190U-PVC pipes (working pressure 4 kg /sqcm.) Rubber (Seal) Ring 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 75 mm diaMaterialeach19.009.00
9977Carriage of materialsMaterialL.S.13.522.2730.69
9999Adhesive, and sundries etc.MaterialL.S.6.762.2715.35
0116Fitter (grade 1)Labourday0.19897.00170.43
0114BeldarLabourday0.37736.00272.32
0100BandhaniLabourday0.08816.0065.28
9999Scaffolding etc.MaterialL.S.18.592.2742.20
TOTAL
1,049.27
Add 1 % Water charges on “W”
10.49
TOTAL
1,059.76
Add GST on “X” (multiplying factor 0.2127)
225.41
TOTAL
1,285.17
Add 15% CPOH on “Y”
192.78
TOTAL
1,477.95
Add Cess @ 1% on “Z”
14.78
Cost of 6.00 metre
1,492.73
Cost of 1.00 metre
248.79
Say
248.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 897. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate