Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes

75 mm diameter
Item number
12.41.1
Analysis basis
6.00 metres
Priced inputs
8
Derived rate
₹248.80/ METRE
D-01/RATE ANALYSISITEM 12.41.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.41.1 (Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes 75 mm diameter) is derived from 8 priced inputs for 6.00 metres and works out to ₹248.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.41.1DETAILS OF COST FOR 6.00 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7188MATU-PVC pipes (working pressure 4 kg / sqcm.) Single socketed pipe 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Single socketed pipe 75 mm diametre674.00444.00
7190MATU-PVC pipes (working pressure 4 kg /sqcm.) Rubber (Seal) Ring 75 mm diaU-PVC pipes (working pressure 4 kg / cm²) Rubber (Seal) Ring 75 mm diaeach19.009.00
9977MATCarriage of materialsL.S.13.522.2730.69
9999MATAdhesive, and sundries etc.L.S.6.762.2715.35
0116LABFitter (grade 1)day0.19897.00170.43
0114LABBeldarday0.37736.00272.32
0100LABBandhaniday0.08816.0065.28
9999MATScaffolding etc.L.S.18.592.2742.20
BUILD-UP TO RATE
TOTAL
1,049.27
Add 1 % Water charges on “W”
+10.49
TOTAL
1,059.76
Add GST on “X” (multiplying factor 0.2127)
+225.41
TOTAL
1,285.17
Add 15% CPOH on “Y”
+192.78
TOTAL
1,477.95
Add Cess @ 1% on “Z”
+14.78
Cost of 6.00 metre
1,492.73
Cost of 1.00 metre
248.79
SAY
₹248.80
D-02/SOURCEPRINTED PAGE 897
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
897

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 897. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.