Skip to main content
R/DAR 2023

Providing, fixing and embedding sand cast iron accessories for rain water pipes in the masonry surrounded with 12 mm thick cement mortar of the same mix, as that of masonry (lead caulking will be paid for separately): Sand cast iron plain shoes

150 mm diameter
Item number
12.40.1.1
Analysis basis
one shoe
Priced inputs
2
Derived rate
₹511.90/ ONE SHOE
D-01/RATE ANALYSISITEM 12.40.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.40.1.1 (Providing, fixing and embedding sand cast iron accessories for rain water pipes in the masonry surrounded with 12 mm thick cement mortar of the same mix, as that of masonry (lead caulking will be paid for separately): Sand cast iron plain shoes : 150 mm diameter) is derived from 2 priced inputs for one shoe and works out to ₹511.90 per one shoe after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.40.1.1DETAILS OF COST FOR ONE SHOE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0966MATSand Cast iron plain shoe 150 mm diaeach1320.00320.00
9988MATCarriage, fixing and mortarL.S.17.552.2739.84
BUILD-UP TO RATE
TOTAL
359.84
Add 1 % Water charges on “W”
+3.60
TOTAL
363.44
Add GST on “X” (multiplying factor 0.2127)
+77.30
TOTAL
440.74
Add 15% CPOH on “Y”
+66.11
TOTAL
506.85
Add Cess @ 1% on “Z”
+5.07
Cost of one shoe
511.92
SAY
₹511.90
D-02/SOURCEPRINTED PAGE 897
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
897

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 897. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.