CPWD Analysis of Rates · Roofing

Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I. rain water pipes embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and cost of cutting holes and making good the walls etc.

150 mm diameter

Item number
12.38.2
Analysis basis
Details of cost of 50 nos.
Priced inputs
19
Derived rate
395.60 / bat clamp

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.38.2 Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I. rain water pipes embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and cost of cutting holes and making good the walls etc. : 150 mm diameter — is derived from 19 priced inputs and works out to ₹395.60 per bat clamp after water charges, GST, CPOH and cess. The full build-up is below.

  • C.C. block 50x0.1x0.1x0.1 = 0.05 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
0886Standard holdar bat clamps for sand cast iron or cast iron pipes 150 mm diaStandard holder bat clamps for sand cast iron or cast iron pipes 150 mm diaMaterialeach5050.002,500.00
9977Carriage of bat clampsMaterialL.S.24.72.2756.07
9999SundriesMaterialL.S.71.52.27162.31
0116Fitter (grade 1)Labourday1.25897.001,121.25
0124Mason 2nd classMason 2nd classLabourday7.5816.006,120.00
0114BeldarLabourday5736.003,680.00
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.0331,425.0047.03
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.0111,400.0015.40
0982Coarse sand (zone III)Materialcum0.0221,450.0031.90
0367Portland Cement (OPC-43 grade)Materialtonne0.0165,156.0082.50
0114BeldarLabourday0.045736.0033.12
0115CoolieLabourday0.032736.0023.55
0101BhistiLabourday0.014816.0011.42
0123Mason 1st classMason 1st classLabourday0.003897.002.69
0124Mason 2nd classMason 2nd classLabourday0.003816.002.45
0128MateLabourday0.002816.001.63
9999Hire charges of machine etc.MaterialL.S.2.62.275.90
9999SundriesMaterialL.S.1.32.272.95
9999SundriesMaterialL.S.1.32.272.95
TOTAL
13,903.12
Add 1 % Water charges on “W”
139.03
TOTAL
14,042.15
Add GST on “X” (multiplying factor 0.2127)
2,986.77
TOTAL
17,028.92
Add 15% CPOH on “Y”
2,554.34
TOTAL
19,583.26
Add Cess @ 1% on “Z”
195.83
Cost of 50 bat clamps
19,779.09
Cost of 1.00 bat clamp
395.58
Say
395.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 895. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.