Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I. rain water pipes embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and cost of cutting holes and making good the walls etc.

100 mm diameter

Item number
12.38.1
Analysis basis
Details of cost of 50 nos.
Priced inputs
19
Derived rate
362.85 / bat clamp

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.38.1 Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I. rain water pipes embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and cost of cutting holes and making good the walls etc. : 100 mm diameter — is derived from 19 priced inputs and works out to ₹362.85 per bat clamp after water charges, GST, CPOH and cess. The full build-up is below.

  • C.C. block 50x0.1x0.1x0.1 = 0.05 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1331M.S.Holder bat clamp of approved design for 100 mm S.C.I. pipeM.S. Holder bat clamp of approved design for 100 mm S.C.I. pipeMaterialeach5027.001,350.00
9977Carriage of bat clampsMaterialL.S.24.72.2756.07
9999SundriesMaterialL.S.71.52.27162.31
0116Fitter (grade 1)Labourday1.25897.001,121.25
0124Mason 2nd classMason 2nd classLabourday7.5816.006,120.00
0114BeldarLabourday5736.003,680.00
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.0331,425.0047.03
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.0111,400.0015.40
0982Coarse sand (zone III)Materialcum0.0221,450.0031.90
0367Portland Cement (OPC-43 grade)Materialtonne0.0165,156.0082.50
0114BeldarLabourday0.045736.0033.12
0115CoolieLabourday0.032736.0023.55
0101BhistiLabourday0.014816.0011.42
0123Mason 1st classMason 1st classLabourday0.003897.002.69
0124Mason 2nd classMason 2nd classLabourday0.003816.002.45
0128MateLabourday0.002816.001.63
9999Hire charges of machine etc.MaterialL.S.2.62.275.90
9999SundriesMaterialL.S.1.32.272.95
9999SundriesMaterialL.S.1.32.272.95
TOTAL
12,753.12
Add 1 % Water charges on “W”
127.53
TOTAL
12,880.65
Add GST on “X” (multiplying factor 0.2127)
2,739.71
TOTAL
15,620.36
Add 15% CPOH on “Y”
2,343.05
TOTAL
17,963.41
Add Cess @ 1% on “Z”
179.63
Cost of 50 bat clamps
18,143.04
Cost of 1.00 bat clamp
362.86
Say
362.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 894. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.