Skip to main content
R/DAR 2023

Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I. rain water pipes embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and cost of cutting holes and making good the walls etc.

100 mm diameter
Item number
12.38.1
Analysis basis
Details of cost of 50 nos.
Priced inputs
19
Derived rate
₹362.85/ BAT CLAMP
D-01/RATE ANALYSISITEM 12.38.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.38.1 (Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I. rain water pipes embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and cost of cutting holes and making good the walls etc. : 100 mm diameter) is derived from 19 priced inputs and works out to ₹362.85 per bat clamp after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • C.C. block 50x0.1x0.1x0.1 = 0.05 cum
ANALYSIS OF RATES · ITEM 12.38.1DETAILS OF COST OF 50 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1331MATM.S.Holder bat clamp of approved design for 100 mm S.C.I. pipeM.S. Holder bat clamp of approved design for 100 mm S.C.I. pipeeach5027.001,350.00
9977MATCarriage of bat clampsL.S.24.72.2756.07
9999MATSundriesL.S.71.52.27162.31
0116LABFitter (grade 1)day1.25897.001,121.25
0124LABMason 2nd classMason 2nd classday7.5816.006,120.00
0114LABBeldarday5736.003,680.00
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum0.0331,425.0047.03
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.0111,400.0015.40
0982MATCoarse sand (zone III)cum0.0221,450.0031.90
0367MATPortland Cement (OPC-43 grade)tonne0.0165,156.0082.50
0114LABBeldarday0.045736.0033.12
0115LABCoolieday0.032736.0023.55
0101LABBhistiday0.014816.0011.42
0123LABMason 1st classMason 1st classday0.003897.002.69
0124LABMason 2nd classMason 2nd classday0.003816.002.45
0128LABMateday0.002816.001.63
9999MATHire charges of machine etc.L.S.2.62.275.90
9999MATSundriesL.S.1.32.272.95
9999MATSundriesL.S.1.32.272.95
BUILD-UP TO RATE
TOTAL
12,753.12
Add 1 % Water charges on “W”
+127.53
TOTAL
12,880.65
Add GST on “X” (multiplying factor 0.2127)
+2,739.71
TOTAL
15,620.36
Add 15% CPOH on “Y”
+2,343.05
TOTAL
17,963.41
Add Cess @ 1% on “Z”
+179.63
Cost of 50 bat clamps
18,143.04
Cost of 1.00 bat clamp
362.86
SAY
₹362.85
D-02/SOURCEPRINTED PAGE 894
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
894

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 894. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.