- ₹164.20/ SPOUT
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.37.1 (Providing and fixing 100 mm diameter and 60 cm long rain water spout in cement mortar 1:4 (1 cement : 4 fine sand) Stone ware spout) is derived from 6 priced inputs for 10 stone and works out to ₹164.20 per spout after water charges, GST, CPOH and cess. The full build-up is below.
- 60cm long
- Labour for fixing and placing in position
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 3004 | MAT | Stone ware spouts 100 mm dia 60 cm long | each | 10 | 46.00 | 460.00 |
| 9977 | MAT | CARRIAGE | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | MAT | Mortar | L.S. | 13.52 | 2.27 | 30.69 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.4 | 816.00 | 326.40 |
| 0114 | LAB | Beldar | day | 0.4 | 736.00 | 294.40 |
| 9999 | MAT | Sundries | L.S. | 5.33 | 2.27 | 12.10 |
- TOTAL
- 1,154.28
- Add 1 % Water charges on “W”
- +11.54
- TOTAL
- 1,165.82
- Add GST on “X” (multiplying factor 0.2127)
- +247.97
- TOTAL
- 1,413.79
- Add 15% CPOH on “Y”
- +212.07
- TOTAL
- 1,625.86
- Add Cess @ 1% on “Z”
- +16.26
- Cost of 10.00 spouts
- 1,642.12
- Cost of 1.00 spout
- 164.21
- SAY
- ₹164.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 893
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 893. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.