Providing and fixing 100 mm diameter and 60 cm long rain water spout in cement mortar 1:4 (1 cement : 4 fine sand)

Stone ware spout
Item number
12.37.1
Analysis basis
10 stone
Priced inputs
6
Derived rate
₹164.20/ SPOUT
D-01/RATE ANALYSISITEM 12.37.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.37.1 (Providing and fixing 100 mm diameter and 60 cm long rain water spout in cement mortar 1:4 (1 cement : 4 fine sand) Stone ware spout) is derived from 6 priced inputs for 10 stone and works out to ₹164.20 per spout after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 60cm long
  • Labour for fixing and placing in position
ANALYSIS OF RATES · ITEM 12.37.1DETAILS OF COST FOR 10 STONE WARE SPOUT OF
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3004MATStone ware spouts 100 mm dia 60 cm longeach1046.00460.00
9977MATCARRIAGEL.S.13.522.2730.69
9999MATMortarL.S.13.522.2730.69
0124LABMason 2nd classMason 2nd classday0.4816.00326.40
0114LABBeldarday0.4736.00294.40
9999MATSundriesL.S.5.332.2712.10
BUILD-UP TO RATE
TOTAL
1,154.28
Add 1 % Water charges on “W”
+11.54
TOTAL
1,165.82
Add GST on “X” (multiplying factor 0.2127)
+247.97
TOTAL
1,413.79
Add 15% CPOH on “Y”
+212.07
TOTAL
1,625.86
Add Cess @ 1% on “Z”
+16.26
Cost of 10.00 spouts
1,642.12
Cost of 1.00 spout
164.21
SAY
₹164.20
D-02/SOURCEPRINTED PAGE 893
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
893

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 893. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.