Thermal Insulation of roofing with Expanded polystyrene fixed with suitable adhesive to the false ceiling as per the directions of the Engineer-in-charge

With Type SE - Self Extinguishing type 50 mm thick
Item number
12.36.2
Analysis basis
Details of cost for 10.00sqm.
Priced inputs
5
Derived rate
₹353.05/ SQM
D-01/RATE ANALYSISITEM 12.36.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.36.2 (Thermal Insulation of roofing with Expanded polystyrene fixed with suitable adhesive to the false ceiling as per the directions of the Engineer-in-charge: With Type SE - Self Extinguishing type 50 mm thick) is derived from 5 priced inputs and works out to ₹353.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Expanded Polystyrens 1x10=10.00sqm. +
  • Total = 11.00sqm.
  • Cost of materials :
  • Add wastage 10% = 1.00sqm.
ANALYSIS OF RATES · ITEM 12.36.2DETAILS OF COST FOR 10.00SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7091MATExpanded polystyrene type - SEExpanded polystyrene type - SE 50 mm thicksqm11148.001,628.00
0314MATBitumen hot sealing compound : grade Akilogram0.2530.007.50
9999MATSundriesL.S.132.2729.51
0111LABCarpenter 1st classday0.5897.00448.50
0114LABBeldarday0.5736.00368.00
BUILD-UP TO RATE
TOTAL
2,481.51
Add 1 % Water charges on “W”
+24.82
TOTAL
2,506.33
Add GST on “X” (multiplying factor 0.2127)
+533.10
TOTAL
3,039.43
Add 15% CPOH on “Y”
+455.91
TOTAL
3,495.34
Add Cess @ 1% on “Z”
+34.95
Cost of 10.00 sqm.
3,530.29
Cost of 1 sqm.
353.03
SAY
₹353.05
D-02/SOURCEPRINTED PAGE 893
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
893

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 893. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.