CPWD Analysis of Rates · Roofing
Thermal Insulation of roofing with Expanded polystyrene fixed with suitable adhesive to the false ceiling as per the directions of the Engineer-in-charge
With Type N - Normal 50 mm thick
- Item number
- 12.36.1
- Analysis basis
- Details of cost for 10.00sqm.
- Priced inputs
- 5
- Derived rate
- ₹321.75 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.36.1 — Thermal Insulation of roofing with Expanded polystyrene fixed with suitable adhesive to the false ceiling as per the directions of the Engineer-in-charge: With Type N - Normal 50 mm thick — is derived from 5 priced inputs and works out to ₹321.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Expanded Polystyrens 1x10=10.00sqm. +
- Total = 11.00sqm.
- Cost of materials :
- Add wastage 10% = 1.00sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7090 | Expanded polystyrene type N- NormalExpanded polystyrene type N- Normal 50 mm thickMaterial | sqm | 11 | 128.00 | 1,408.00 |
| 0314 | Bitumen hot sealing compound : grade AMaterial | kilogram | 0.25 | 30.00 | 7.50 |
| 9999 | SundriesMaterial | L.S. | 13 | 2.27 | 29.51 |
| 0111 | Carpenter 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 0114 | BeldarLabour | day | 0.5 | 736.00 | 368.00 |
- TOTAL
- 2,261.51
- Add 1 % Water charges on “W”
- 22.62
- TOTAL
- 2,284.13
- Add GST on “X” (multiplying factor 0.2127)
- 485.83
- TOTAL
- 2,769.96
- Add 15% CPOH on “Y”
- 415.49
- TOTAL
- 3,185.45
- Add Cess @ 1% on “Z”
- 31.85
- Cost of 10.00 sqm.
- 3,217.30
- Cost of 1.00 sqm.
- 321.73
- Say
- 321.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 892. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.