Skip to main content

CPWD Analysis of Rates · Roofing

Providing and fixing thermal insulation with Resin Bonded Fibre glass wool conforming to IS: 8183. Density 16 kg/m³, 50 mm thick, wrapped in 200G Virgin Polythene bags placed over existing false ceiling and held in position by criss-crossing GI wire

Item number
12.35
Analysis basis
Details of cost for 10.00sqm.
Priced inputs
4
Derived rate
297.25 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.35 Providing and fixing thermal insulation with Resin Bonded Fibre glass wool conforming to IS: 8183. Density 16 kg/m³, 50 mm thick, wrapped in 200G Virgin Polythene bags placed over existing false ceiling and held in position by criss-crossing GI wire — is derived from 4 priced inputs and works out to ₹297.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Area for 10.00sqm. (Finished surface) =
  • 10.00sqm.+
  • 1.00sqm.
  • Total = 11.00sqm.
  • Add 10% for overlappings & wastage =
CodeInputUnitQuantityRate (INR)Amount (INR)
7231Resin Bonded Glass wool 16 kg/m³ 50 mm thickResin Bonded Glass wool 16 kg/m³ : 50 mm thickMaterialsqm11105.001,155.00
9999Sundries including GI wire 20 SWG and Virgin polythene bags 200 gramMaterialL.S.522.27118.04
0111Carpenter 1st classLabourday0.5897.00448.50
0114BeldarLabourday0.5736.00368.00
TOTAL
2,089.54
Add 1 % Water charges on “W”
20.90
TOTAL
2,110.44
Add GST on “X” (multiplying factor 0.2127)
448.89
TOTAL
2,559.33
Add 15% CPOH on “Y”
383.90
TOTAL
2,943.23
Add Cess @ 1% on “Z”
29.43
Cost of 10.00 sqm.
2,972.66
Cost of 1.00 sqm.
297.27
Say
297.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 892. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works