CPWD Analysis of Rates · Roofing
Providing fixing thermal insulation of ceiling (under deck insulation) with Resin Bonded Fibre glass wool conforming to IS : 8183, density 24kg / m3, 50mm thick, wrapped in 200 G Virgin Polythene bags, fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire mesh of 12.5 mm x 24 gauge wire mesh, for top most ceiling of building
- Item number
- 12.34
- Analysis basis
- Details of cost for 10.00sqm.
- Priced inputs
- 5
- Derived rate
- ₹703.05 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.34 — Providing fixing thermal insulation of ceiling (under deck insulation) with Resin Bonded Fibre glass wool conforming to IS : 8183, density 24kg / m3, 50mm thick, wrapped in 200 G Virgin Polythene bags, fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire mesh of 12.5 mm x 24 gauge wire mesh, for top most ceiling of building — is derived from 5 priced inputs and works out to ₹703.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Area for 10.00sqm. (Finished surface) =
- 10.00sqm.+
- 1.00sqm.
- Total = 11.00sqm.
- Add 10% for overlappings & wastage =
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7232 | Resin Bonded Glass wool 24 kg/m³ 50 mm thickResin Bonded Glass wool 24 kg/m³ : 50 mm thickMaterial | sqm | 11 | 140.00 | 1,540.00 |
| 9999 | Sundries including GI wire 20 SWG and Virgin polythene bags 200 gramMaterial | L.S. | 104 | 2.27 | 236.08 |
| 9999 | GI chiken mesh 12.5mm x 24 SWGMaterial | L.S. | 351 | 2.27 | 796.77 |
| 0111 | Carpenter 1st classLabour | day | 1 | 897.00 | 897.00 |
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
- TOTAL
- 4,941.85
- Add 1 % Water charges on “W”
- 49.42
- TOTAL
- 4,991.27
- Add GST on “X” (multiplying factor 0.2127)
- 1,061.64
- TOTAL
- 6,052.91
- Add 15% CPOH on “Y”
- 907.94
- TOTAL
- 6,960.85
- Add Cess @ 1% on “Z”
- 69.61
- Cost of 10.00 sqm.
- 7,030.46
- Cost of 1.00 sqm.
- 703.05
- Say
- 703.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 891. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.