Providing lead caulked joints to sand cast iron rain water pipes and fittings

100 mm dia Pipe
Item number
12.39.1
Analysis basis
one joint
Priced inputs
7
Derived rate
₹580.50/ JOINT
D-01/RATE ANALYSISITEM 12.39.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.39.1 (Providing lead caulked joints to sand cast iron rain water pipes and fittings: 100 mm dia Pipe) is derived from 7 priced inputs for one joint and works out to ₹580.50 per joint after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.39.1DETAILS OF COST FOR ONE JOINT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0865MATPig leadkilogram0.98180.00176.40
1001MATSpun yarnkilogram0.1160.006.60
9999MATKerosene oil fuel and sundriesL.S.13.522.2730.69
9977MATCarriage of materialsL.S.1.432.273.25
0116LABFitter (grade 1)day0.06897.0053.82
0117LABAssistant Fitter or 2nd class Fitterday0.06816.0048.96
0114LABBeldarday0.12736.0088.32
BUILD-UP TO RATE
TOTAL
408.04
Add 1 % Water charges on “W”
+4.08
TOTAL
412.12
Add GST on “X” (multiplying factor 0.2127)
+87.66
TOTAL
499.78
Add 15% CPOH on “Y”
+74.97
TOTAL
574.75
Add Cess @ 1% on “Z”
+5.75
Cost of 1.00 joint
580.50
SAY
₹580.50
D-02/SOURCEPRINTED PAGE 896
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
896

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 896. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.