Extra for Circular cutting including wastages in ceiling with: Standard quality hard board sheet

3 mm thick
Item number
12.27.5.1
Analysis basis
15.71 metre
Priced inputs
10
Derived rate
₹470.10/ METRE
D-01/RATE ANALYSISITEM 12.27.5.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.27.5.1 (Extra for Circular cutting including wastages in ceiling with: Standard quality hard board sheet: 3 mm thick) is derived from 10 priced inputs for 15.71 metre and works out to ₹470.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 0.5 metre dia. each = 10x22/7x0.5=15.71m
  • Area = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +
  • Wastage @ 10% = 0.19 sqm.
  • Total = 2.15 sqm.
ANALYSIS OF RATES · ITEM 12.27.5.1DETAILS OF COST FOR 15.71 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0994MATStandard quality hard board sheet 3 mm thicksqm2.15145.00311.75
9977MATCarriageL.S.2.732.276.20
9999MATNailsL.S.5.332.2712.10
0111LABCarpenter 1st classday0.49897.00439.53
0114LABBeldarday0.39736.00287.04
9999MATScaffoldingL.S.6.112.2713.87
9999MATSundriesL.S.6.112.2713.87
0111LABCarpenter 1st classday2.5897.002,242.50
0114LABBeldarday2.5736.001,840.00
9999MATScaffoldingL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
5,191.35
Add 1 % Water charges on “W”
+51.91
TOTAL
5,243.26
Add GST on “X” (multiplying factor 0.2127)
+1,115.24
TOTAL
6,358.50
Add 15% CPOH on “Y”
+953.78
TOTAL
7,312.28
Add Cess @ 1% on “Z”
+73.12
Cost of 15.71 metre
7,385.40
Cost of 1.00 metre
470.11
SAY
₹470.10
D-02/SOURCEPRINTED PAGE 887
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
887

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 887. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.