Extra for Circular cutting including wastages in ceiling with: Flame retardant face insulating board

12 mm thick

Item number
12.27.4.1
Analysis basis
Details of cost for 15.71 metre
Priced inputs
10
Derived rate
511.50 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.27.4.1 Extra for Circular cutting including wastages in ceiling with: Flame retardant face insulating board: 12 mm thick — is derived from 10 priced inputs for 15.71 metre and works out to ₹511.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 0.5 metre dia. each = 10x22/7x0.5=15.71m
  • Area = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +
  • Wastage @ 10% = 0.19 sqm.
  • Total = 2.15 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
0336Flame retardent face insulating board: 12 mm thickFlame retardant face insulating board: 12 mm thickMaterialsqm2.15357.00767.55
9977CarriageMaterialL.S.3.382.277.67
9999NailsMaterialL.S.5.332.2712.10
0111Carpenter 1st classLabourday0.49897.00439.53
0114BeldarLabourday0.39736.00287.04
9999ScaffoldingMaterialL.S.6.112.2713.87
9999SundriesMaterialL.S.6.112.2713.87
0111Carpenter 1st classLabourday2.5897.002,242.50
0114BeldarLabourday2.5736.001,840.00
9999ScaffoldingMaterialL.S.10.792.2724.49
TOTAL
5,648.62
Add 1 % Water charges on “W”
56.49
TOTAL
5,705.11
Add GST on “X” (multiplying factor 0.2127)
1,213.48
TOTAL
6,918.59
Add 15% CPOH on “Y”
1,037.79
TOTAL
7,956.38
Add Cess @ 1% on “Z”
79.56
Cost of 15.71 metre
8,035.94
Cost of 1.00 metre
511.52
Say
511.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 886. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.