Extra for Circular cutting including wastages in ceiling with: Flame retardant face insulating board
- Item number
- 12.27.4.1
- Analysis basis
- 15.71 metre
- Priced inputs
- 10
- Derived rate
- ₹511.50/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.27.4.1 (Extra for Circular cutting including wastages in ceiling with: Flame retardant face insulating board: 12 mm thick) is derived from 10 priced inputs for 15.71 metre and works out to ₹511.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 0.5 metre dia. each = 10x22/7x0.5=15.71m
- Area = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +
- Wastage @ 10% = 0.19 sqm.
- Total = 2.15 sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0336 | MAT | Flame retardent face insulating board: 12 mm thickFlame retardant face insulating board: 12 mm thick | sqm | 2.15 | 357.00 | 767.55 |
| 9977 | MAT | Carriage | L.S. | 3.38 | 2.27 | 7.67 |
| 9999 | MAT | Nails | L.S. | 5.33 | 2.27 | 12.10 |
| 0111 | LAB | Carpenter 1st class | day | 0.49 | 897.00 | 439.53 |
| 0114 | LAB | Beldar | day | 0.39 | 736.00 | 287.04 |
| 9999 | MAT | Scaffolding | L.S. | 6.11 | 2.27 | 13.87 |
| 9999 | MAT | Sundries | L.S. | 6.11 | 2.27 | 13.87 |
| 0111 | LAB | Carpenter 1st class | day | 2.5 | 897.00 | 2,242.50 |
| 0114 | LAB | Beldar | day | 2.5 | 736.00 | 1,840.00 |
| 9999 | MAT | Scaffolding | L.S. | 10.79 | 2.27 | 24.49 |
- TOTAL
- 5,648.62
- Add 1 % Water charges on “W”
- +56.49
- TOTAL
- 5,705.11
- Add GST on “X” (multiplying factor 0.2127)
- +1,213.48
- TOTAL
- 6,918.59
- Add 15% CPOH on “Y”
- +1,037.79
- TOTAL
- 7,956.38
- Add Cess @ 1% on “Z”
- +79.56
- Cost of 15.71 metre
- 8,035.94
- Cost of 1.00 metre
- 511.52
- SAY
- ₹511.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 886
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 886. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.