Skip to main content
R/DAR 2023

Providing and fixing plain multipurpose cement board(Hight pressure steam cured) with suitable screws for cement particle board in ceiling etc. complete (frame work to be paid seperatately)

6 mm thick Cement bonded wood particle board as per IS:14276
Item number
12.26.2
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹890.65/ SQM
D-01/RATE ANALYSISITEM 12.26.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.26.2 (Providing and fixing plain multipurpose cement board(Hight pressure steam cured) with suitable screws for cement particle board in ceiling etc. complete (frame work to be paid seperatately) 6 mm thick Cement bonded wood particle board as per IS:14276) is derived from 7 priced inputs for 10 sqm and works out to ₹890.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 10.00 sqm + 1.00 sqm (Add wastage 10%)
  • Total = 11.00 sqm
ANALYSIS OF RATES · ITEM 12.26.2DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0242MAT6 mm thick multi purpose cement bonded wood particle board6 mm thick mulitipurpose cement bonded wood particle board conforming to IS : 14276sqm11210.002,310.00
9977MATCarriageL.S.14.952.2733.94
9999MATNailsL.S.26.912.2761.09
0111LABCarpenter 1st classday2.5897.002,242.50
0114LABBeldarday2736.001,472.00
9999MATScaffoldingL.S.31.072.2770.53
9999MATSundriesL.S.31.072.2770.53
BUILD-UP TO RATE
TOTAL
6,260.59
Add 1 % Water charges on “W”
+62.61
TOTAL
6,323.20
Add GST on “X” (multiplying factor 0.2127)
+1,344.94
TOTAL
7,668.14
Add 15% CPOH on “Y”
+1,150.22
TOTAL
8,818.36
Add Cess @ 1% on “Z”
+88.18
Cost of 10 sqm
8,906.54
Cost of 1 sqm
890.65
SAY
₹890.65
D-02/SOURCEPRINTED PAGE 883
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
883

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 883. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.