CPWD Analysis of Rates · Roofing
Providing and fixing plain multipurpose cement board(Hight pressure steam cured) with suitable screws for cement particle board in ceiling etc. complete (frame work to be paid seperatately)
6 mm thick Cement bonded wood particle board as per IS:14276
- Item number
- 12.26.2
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 7
- Derived rate
- ₹890.65 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.26.2 — Providing and fixing plain multipurpose cement board(Hight pressure steam cured) with suitable screws for cement particle board in ceiling etc. complete (frame work to be paid seperatately) 6 mm thick Cement bonded wood particle board as per IS:14276 — is derived from 7 priced inputs for 10 sqm and works out to ₹890.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 10.00 sqm + 1.00 sqm (Add wastage 10%)
- Total = 11.00 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0242 | 6 mm thick multi purpose cement bonded wood particle board6 mm thick mulitipurpose cement bonded wood particle board conforming to IS : 14276Material | sqm | 11 | 210.00 | 2,310.00 |
| 9977 | CarriageMaterial | L.S. | 14.95 | 2.27 | 33.94 |
| 9999 | NailsMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 0111 | Carpenter 1st classLabour | day | 2.5 | 897.00 | 2,242.50 |
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 9999 | ScaffoldingMaterial | L.S. | 31.07 | 2.27 | 70.53 |
| 9999 | SundriesMaterial | L.S. | 31.07 | 2.27 | 70.53 |
- TOTAL
- 6,260.59
- Add 1 % Water charges on “W”
- 62.61
- TOTAL
- 6,323.20
- Add GST on “X” (multiplying factor 0.2127)
- 1,344.94
- TOTAL
- 7,668.14
- Add 15% CPOH on “Y”
- 1,150.22
- TOTAL
- 8,818.36
- Add Cess @ 1% on “Z”
- 88.18
- Cost of 10 sqm
- 8,906.54
- Cost of 1 sqm
- 890.65
- Say
- 890.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 883. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works