Providing and fixing plain multipurpose cement board(Hight pressure steam cured) with suitable screws for cement particle board in ceiling etc. complete (frame work to be paid seperatately)

6 mm thick Cement fiber board, Type-B, Category-III as per IS: 14862 : 2000
Item number
12.26.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹921.95/ SQM
D-01/RATE ANALYSISITEM 12.26.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.26.1 (Providing and fixing plain multipurpose cement board(Hight pressure steam cured) with suitable screws for cement particle board in ceiling etc. complete (frame work to be paid seperatately) 6 mm thick Cement fiber board, Type-B, Category-III as per IS: 14862 : 2000) is derived from 7 priced inputs for 10 sqm and works out to ₹921.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • including 10% wastage = 11.00 sqm
ANALYSIS OF RATES · ITEM 12.26.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0236MATFibre reinforced by organic fibres and/or inorganic synthetic fibres cement board 6mm thick, Type-B, Category-III as per IS: 14862 : 20006 mm thick Non - Asbestos multi purpose fibre cement board Type-B, Category-III as per IS: 14862:2000sqm11230.002,530.00
9977MATCarriageL.S.14.952.2733.94
9999MATNailsL.S.26.912.2761.09
0111LABCarpenter 1st classday2.5897.002,242.50
0114LABBeldarday2736.001,472.00
9999MATScaffoldingL.S.31.072.2770.53
9999MATSundriesL.S.31.072.2770.53
BUILD-UP TO RATE
TOTAL
6,480.59
Add 1 % Water charges on “W”
+64.81
TOTAL
6,545.40
Add GST on “X” (multiplying factor 0.2127)
+1,392.21
TOTAL
7,937.61
Add 15% CPOH on “Y”
+1,190.64
TOTAL
9,128.25
Add Cess @ 1% on “Z”
+91.28
Cost of 10.00 sqm.
9,219.53
Cost of 1.00 sqm.
921.95
SAY
₹921.95
D-02/SOURCEPRINTED PAGE 883
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
883

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 883. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.