Skip to main content

CPWD Analysis of Rates · Roofing

Providing and fixing plain multipurpose cement board(Hight pressure steam cured) with suitable screws for cement particle board in ceiling etc. complete (frame work to be paid seperatately)

6 mm thick Cement fiber board, Type-B, Category-III as per IS: 14862 : 2000

Item number
12.26.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
7
Derived rate
921.95 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.26.1 Providing and fixing plain multipurpose cement board(Hight pressure steam cured) with suitable screws for cement particle board in ceiling etc. complete (frame work to be paid seperatately) 6 mm thick Cement fiber board, Type-B, Category-III as per IS: 14862 : 2000 — is derived from 7 priced inputs for 10 sqm and works out to ₹921.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • including 10% wastage = 11.00 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
0236Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement board 6mm thick, Type-B, Category-III as per IS: 14862 : 20006 mm thick Non - Asbestos multi purpose fibre cement board Type-B, Category-III as per IS: 14862:2000Materialsqm11230.002,530.00
9977CarriageMaterialL.S.14.952.2733.94
9999NailsMaterialL.S.26.912.2761.09
0111Carpenter 1st classLabourday2.5897.002,242.50
0114BeldarLabourday2736.001,472.00
9999ScaffoldingMaterialL.S.31.072.2770.53
9999SundriesMaterialL.S.31.072.2770.53
TOTAL
6,480.59
Add 1 % Water charges on “W”
64.81
TOTAL
6,545.40
Add GST on “X” (multiplying factor 0.2127)
1,392.21
TOTAL
7,937.61
Add 15% CPOH on “Y”
1,190.64
TOTAL
9,128.25
Add Cess @ 1% on “Z”
91.28
Cost of 10.00 sqm.
9,219.53
Cost of 1.00 sqm.
921.95
Say
921.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 883. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works