Providing and fixing flat pressed 3 layer medium density particle board or graded particle board (Grade I) IS: 3087 marked, in ceiling with necessary nails etc. complete (frame work to be paid separately)
- Item number
- 12.25.1
- Analysis basis
- 10 sqm
- Priced inputs
- 7
- Derived rate
- ₹1,070.60/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.25.1 (Providing and fixing flat pressed 3 layer medium density particle board or graded particle board (Grade I) IS: 3087 marked, in ceiling with necessary nails etc. complete (frame work to be paid separately): 12 mm thick) is derived from 7 priced inputs for 10 sqm and works out to ₹1,070.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- including 10% wastage = 11.00 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0341 | MAT | Flat pressed 3 layer particle board (medium density) Grade I :12 mm thickFlat pressed three layer or graded wood particle board (medium density) exterior grade Grade 1, FPT-1, conforming and marked to IS:3087 12 mm thick | sqm | 11 | 325.00 | 3,575.00 |
| 9977 | MAT | Carriage | L.S. | 14.95 | 2.27 | 33.94 |
| 9999 | MAT | Nails | L.S. | 26.91 | 2.27 | 61.09 |
| 0111 | LAB | Carpenter 1st class | day | 2.5 | 897.00 | 2,242.50 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
| 9999 | MAT | Scaffolding | L.S. | 31.07 | 2.27 | 70.53 |
| 9999 | MAT | Sundries | L.S. | 31.07 | 2.27 | 70.53 |
- TOTAL
- 7,525.59
- Add 1 % Water charges on “W”
- +75.26
- TOTAL
- 7,600.85
- Add GST on “X” (multiplying factor 0.2127)
- +1,616.70
- TOTAL
- 9,217.55
- Add 15% CPOH on “Y”
- +1,382.63
- TOTAL
- 10,600.18
- Add Cess @ 1% on “Z”
- +106.00
- Cost of 10.00 sqm.
- 10,706.18
- Cost of 1.00 sqm.
- 1,070.62
- SAY
- ₹1,070.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 882
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 882. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.