Providing and fixing flat pressed 3 layer medium density particle board or graded particle board (Grade I) IS: 3087 marked, in ceiling with necessary nails etc. complete (frame work to be paid separately)

12 mm thick
Item number
12.25.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹1,070.60/ SQM
D-01/RATE ANALYSISITEM 12.25.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.25.1 (Providing and fixing flat pressed 3 layer medium density particle board or graded particle board (Grade I) IS: 3087 marked, in ceiling with necessary nails etc. complete (frame work to be paid separately): 12 mm thick) is derived from 7 priced inputs for 10 sqm and works out to ₹1,070.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • including 10% wastage = 11.00 sqm
ANALYSIS OF RATES · ITEM 12.25.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0341MATFlat pressed 3 layer particle board (medium density) Grade I :12 mm thickFlat pressed three layer or graded wood particle board (medium density) exterior grade Grade 1, FPT-1, conforming and marked to IS:3087 12 mm thicksqm11325.003,575.00
9977MATCarriageL.S.14.952.2733.94
9999MATNailsL.S.26.912.2761.09
0111LABCarpenter 1st classday2.5897.002,242.50
0114LABBeldarday2736.001,472.00
9999MATScaffoldingL.S.31.072.2770.53
9999MATSundriesL.S.31.072.2770.53
BUILD-UP TO RATE
TOTAL
7,525.59
Add 1 % Water charges on “W”
+75.26
TOTAL
7,600.85
Add GST on “X” (multiplying factor 0.2127)
+1,616.70
TOTAL
9,217.55
Add 15% CPOH on “Y”
+1,382.63
TOTAL
10,600.18
Add Cess @ 1% on “Z”
+106.00
Cost of 10.00 sqm.
10,706.18
Cost of 1.00 sqm.
1,070.62
SAY
₹1,070.60
D-02/SOURCEPRINTED PAGE 882
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
882

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 882. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.