Skip to main content

CPWD Analysis of Rates · Roofing

Providing and fixing flat pressed 3 layer medium density particle board or graded particle board (Grade I) IS: 3087 marked, in ceiling with necessary nails etc. complete (frame work to be paid separately)

12 mm thick

Item number
12.25.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
7
Derived rate
1,070.60 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.25.1 Providing and fixing flat pressed 3 layer medium density particle board or graded particle board (Grade I) IS: 3087 marked, in ceiling with necessary nails etc. complete (frame work to be paid separately): 12 mm thick — is derived from 7 priced inputs for 10 sqm and works out to ₹1,070.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • including 10% wastage = 11.00 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
0341Flat pressed 3 layer particle board (medium density) Grade I :12 mm thickFlat pressed three layer or graded wood particle board (medium density) exterior grade Grade 1, FPT-1, conforming and marked to IS:3087 12 mm thickMaterialsqm11325.003,575.00
9977CarriageMaterialL.S.14.952.2733.94
9999NailsMaterialL.S.26.912.2761.09
0111Carpenter 1st classLabourday2.5897.002,242.50
0114BeldarLabourday2736.001,472.00
9999ScaffoldingMaterialL.S.31.072.2770.53
9999SundriesMaterialL.S.31.072.2770.53
TOTAL
7,525.59
Add 1 % Water charges on “W”
75.26
TOTAL
7,600.85
Add GST on “X” (multiplying factor 0.2127)
1,616.70
TOTAL
9,217.55
Add 15% CPOH on “Y”
1,382.63
TOTAL
10,600.18
Add Cess @ 1% on “Z”
106.00
Cost of 10.00 sqm.
10,706.18
Cost of 1.00 sqm.
1,070.62
Say
1,070.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 882. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works