Providing and fixing insulating board ceiling of approved quality with necessary nails etc. complete (frame work to be paid separately) : Flame retardant face insulating board

12 mm thick
Item number
12.24.3.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹1,121.55/ SQM
D-01/RATE ANALYSISITEM 12.24.3.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.24.3.1 (Providing and fixing insulating board ceiling of approved quality with necessary nails etc. complete (frame work to be paid separately) : Flame retardant face insulating board 12 mm thick) is derived from 7 priced inputs for 10 sqm and works out to ₹1,121.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • including 10% wastage = 11.00 sqm
ANALYSIS OF RATES · ITEM 12.24.3.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0336MATFlame retardent face insulating board: 12 mm thickFlame retardant face insulating board: 12 mm thicksqm11357.003,927.00
9977MATCarriage of materialL.S.17.552.2739.84
9999MATNailsL.S.26.912.2761.09
0111LABCarpenter 1st classday2.5897.002,242.50
0114LABBeldarday2736.001,472.00
9999MATScaffoldingL.S.31.072.2770.53
9999MATSundriesL.S.31.072.2770.53
BUILD-UP TO RATE
TOTAL
7,883.49
Add 1 % Water charges on “W”
+78.83
TOTAL
7,962.32
Add GST on “X” (multiplying factor 0.2127)
+1,693.59
TOTAL
9,655.91
Add 15% CPOH on “Y”
+1,448.39
TOTAL
11,104.30
Add Cess @ 1% on “Z”
+111.04
Cost of 10.00 sqm.
11,215.34
Cost of 1.00 sqm.
1,121.53
SAY
₹1,121.55
D-02/SOURCEPRINTED PAGE 882
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
882

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 882. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.