CPWD Analysis of Rates · Roofing
Providing and fixing insulating board ceiling of approved quality with necessary nails etc. complete (frame work to be paid separately) : Flame retardant face insulating board
12 mm thick
- Item number
- 12.24.3.1
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 7
- Derived rate
- ₹1,121.55 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.24.3.1 — Providing and fixing insulating board ceiling of approved quality with necessary nails etc. complete (frame work to be paid separately) : Flame retardant face insulating board 12 mm thick — is derived from 7 priced inputs for 10 sqm and works out to ₹1,121.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- including 10% wastage = 11.00 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0336 | Flame retardent face insulating board: 12 mm thickFlame retardant face insulating board: 12 mm thickMaterial | sqm | 11 | 357.00 | 3,927.00 |
| 9977 | Carriage of materialMaterial | L.S. | 17.55 | 2.27 | 39.84 |
| 9999 | NailsMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 0111 | Carpenter 1st classLabour | day | 2.5 | 897.00 | 2,242.50 |
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 9999 | ScaffoldingMaterial | L.S. | 31.07 | 2.27 | 70.53 |
| 9999 | SundriesMaterial | L.S. | 31.07 | 2.27 | 70.53 |
- TOTAL
- 7,883.49
- Add 1 % Water charges on “W”
- 78.83
- TOTAL
- 7,962.32
- Add GST on “X” (multiplying factor 0.2127)
- 1,693.59
- TOTAL
- 9,655.91
- Add 15% CPOH on “Y”
- 1,448.39
- TOTAL
- 11,104.30
- Add Cess @ 1% on “Z”
- 111.04
- Cost of 10.00 sqm.
- 11,215.34
- Cost of 1.00 sqm.
- 1,121.53
- Say
- 1,121.55
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 882. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.