CPWD Analysis of Rates · Roofing
Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 10 mm and down gauge), including finishing with cement mortar 1:3 (1 cement : 3 fine sand) as per standard design
In 75x75 mm deep chase
- Item number
- 12.21.1
- Analysis basis
- Details of cost for 100 metre cement con-
- Priced inputs
- 24
- Derived rate
- ₹305.15 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.21.1 — Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 10 mm and down gauge), including finishing with cement mortar 1:3 (1 cement : 3 fine sand) as per standard design : In 75x75 mm deep chase — is derived from 24 priced inputs for 100 metre and works out to ₹305.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- crete
- Cement mortar for grouting 1:3 (1 cement :
- 3 fine sand)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0297 | Stone Aggregate (Single size) : 10 mm nominal sizeMaterial | cum | 0.836 | 1,400.00 | 1,170.40 |
| 0982 | Coarse sand (zone III)Material | cum | 0.418 | 1,450.00 | 606.10 |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.3 | 5,156.00 | 1,546.80 |
| 0114 | BeldarLabour | day | 0.85 | 736.00 | 625.60 |
| 0115 | CoolieLabour | day | 0.56 | 736.00 | 412.16 |
| 0101 | BhistiLabour | day | 0.25 | 816.00 | 204.00 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.05 | 897.00 | 44.85 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.05 | 816.00 | 40.80 |
| 0128 | MateLabour | day | 0.037 | 816.00 | 30.19 |
| 9999 | Hire and running charge of mechanical mixerMaterial | L.S. | 24.7 | 2.27 | 56.07 |
| 9999 | SundriesMaterial | L.S. | 13 | 2.27 | 29.51 |
| 0123 | Mason 1st classMason 1st classLabour | day | 1.5 | 897.00 | 1,345.50 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 1.5 | 816.00 | 1,224.00 |
| 9999 | SundriesMaterial | L.S. | 50.7 | 2.27 | 115.09 |
| 0123 | Mason 1st classMason 1st classLabour | day | 2.5 | 897.00 | 2,242.50 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 2.5 | 816.00 | 2,040.00 |
| 0114 | BeldarLabour | day | 10 | 736.00 | 7,360.00 |
| 9977 | CarriageMaterial | L.S. | 80.6 | 2.27 | 182.96 |
| Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3Sub-analysis | cum | 0.09 | 4,379.05 | 394.11 | |
| 0155 | Mason (average)Labour | day | 0.81 | 857.00 | 694.17 |
| 0115 | CoolieLabour | day | 1.01 | 736.00 | 743.36 |
| 0101 | BhistiLabour | day | 0.33 | 816.00 | 269.28 |
| 9999 | Hire and running charges of mechanical mixerMaterial | L.S. | 16.9 | 2.27 | 38.36 |
| 9999 | SundriesMaterial | L.S. | 14.3 | 2.27 | 32.46 |
- TOTAL
- 21,448.27
- Add 1 % Water charges on “W”
- 214.48
- TOTAL
- 21,662.75
- Add GST on “X” (multiplying factor 0.2127)
- 4,607.67
- TOTAL
- 26,270.42
- Add 15% CPOH on “Y”
- 3,940.56
- TOTAL
- 30,210.98
- Add Cess @ 1% on “Z”
- 302.11
- Cost of 100 metre
- 30,513.09
- Cost of 1.00 metre
- 305.13
- Say
- 305.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 877. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.