Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 10 mm and down gauge), including finishing with cement mortar 1:3 (1 cement : 3 fine sand) as per standard design

In 75x75 mm deep chase
Item number
12.21.1
Analysis basis
100 metre
Priced inputs
24
Derived rate
₹305.15/ METRE
D-01/RATE ANALYSISITEM 12.21.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.21.1 (Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 10 mm and down gauge), including finishing with cement mortar 1:3 (1 cement : 3 fine sand) as per standard design : In 75x75 mm deep chase) is derived from 24 priced inputs for 100 metre and works out to ₹305.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • crete
  • Cement mortar for grouting 1:3 (1 cement :
  • 3 fine sand)
ANALYSIS OF RATES · ITEM 12.21.1DETAILS OF COST FOR 100 METRE CEMENT CON-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.8361,400.001,170.40
0982MATCoarse sand (zone III)cum0.4181,450.00606.10
0367MATPortland Cement (OPC-43 grade)tonne0.35,156.001,546.80
0114LABBeldarday0.85736.00625.60
0115LABCoolieday0.56736.00412.16
0101LABBhistiday0.25816.00204.00
0123LABMason 1st classMason 1st classday0.05897.0044.85
0124LABMason 2nd classMason 2nd classday0.05816.0040.80
0128LABMateday0.037816.0030.19
9999MATHire and running charge of mechanical mixerL.S.24.72.2756.07
9999MATSundriesL.S.132.2729.51
0123LABMason 1st classMason 1st classday1.5897.001,345.50
0124LABMason 2nd classMason 2nd classday1.5816.001,224.00
9999MATSundriesL.S.50.72.27115.09
0123LABMason 1st classMason 1st classday2.5897.002,242.50
0124LABMason 2nd classMason 2nd classday2.5816.002,040.00
0114LABBeldarday10736.007,360.00
9977MATCarriageL.S.80.62.27182.96
SUBRate as per Item Number 3.3 of SH: MortarsRate as per item 3.3cum0.094,379.05394.11
0155LABMason (average)day0.81857.00694.17
0115LABCoolieday1.01736.00743.36
0101LABBhistiday0.33816.00269.28
9999MATHire and running charges of mechanical mixerL.S.16.92.2738.36
9999MATSundriesL.S.14.32.2732.46
BUILD-UP TO RATE
TOTAL
21,448.27
Add 1 % Water charges on “W”
+214.48
TOTAL
21,662.75
Add GST on “X” (multiplying factor 0.2127)
+4,607.67
TOTAL
26,270.42
Add 15% CPOH on “Y”
+3,940.56
TOTAL
30,210.98
Add Cess @ 1% on “Z”
+302.11
Cost of 100 metre
30,513.09
Cost of 1.00 metre
305.13
SAY
₹305.15
D-02/SOURCEPRINTED PAGE 877
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
877

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 877. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.