CPWD Analysis of Rates · Roofing

Making khurras 45x45 cm with average minimum thickness of 5 cm cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 20 mm nominal size) over P.V.C. sheet 1 m x1 m x 400 micron, finished with 12 mm cement plaster 1:3 (1 cement : 3 coarse sand) and a coat of neat cement, rounding the edges and making and finishing the outlet complete

Item number
12.22
Analysis basis
Details of cost for 10 nos.
Priced inputs
23
Derived rate
298.25 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.22 Making khurras 45x45 cm with average minimum thickness of 5 cm cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 20 mm nominal size) over P.V.C. sheet 1 m x1 m x 400 micron, finished with 12 mm cement plaster 1:3 (1 cement : 3 coarse sand) and a coat of neat cement, rounding the edges and making and finishing the outlet complete — is derived from 23 priced inputs for 10 nos and works out to ₹298.25 per no after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.0671,425.0095.48
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.0221,400.0030.80
0982Coarse sand (zone III)Materialcum0.0441,450.0063.80
0367Portland Cement (OPC-43 grade)Materialtonne0.0325,156.00164.99
0114BeldarLabourday0.09736.0066.24
0115CoolieLabourday0.06736.0044.16
0101BhistiLabourday0.027816.0022.03
0123Mason 1st classMason 1st classLabourday0.005897.004.49
0124Mason 2nd classMason 2nd classLabourday0.005816.004.08
0128MateLabourday0.004816.003.26
9999Hire and running charge of mechanical mixerMaterialL.S.2.62.275.90
9999SundriesMaterialL.S.1.32.272.95
3002Polyvinyle chloride sheet 400 micron thickPolyvinyl chloride sheet 400 micron thickMaterialsqm1047.00470.00
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.0414,881.95200.16
0155Mason (average)Labourday0.235857.00201.40
0115CoolieLabourday0.235736.00172.96
0101BhistiLabourday0.078816.0063.65
9999SundriesMaterialL.S.3.92.278.85
0367Portland Cement (OPC-43 grade)Materialtonne0.0065,156.0030.94
0155Mason (average)Labourday0.08857.0068.56
0115CoolieLabourday0.08736.0058.88
9999Rounding of edges and making outletMaterialL.S.2.62.275.90
9999SundriesMaterialL.S.135.22.27306.90
TOTAL
2,096.38
Add 1 % Water charges on “W”
20.96
TOTAL
2,117.34
Add GST on “X” (multiplying factor 0.2127)
450.36
TOTAL
2,567.70
Add 15% CPOH on “Y”
385.16
TOTAL
2,952.86
Add Cess @ 1% on “Z”
29.53
Cost of 10 nos.
2,982.39
Cost of 1 no.
298.24
Say
298.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 878. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.