Making khurras 45x45 cm with average minimum thickness of 5 cm cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 20 mm nominal size) over P.V.C. sheet 1 m x1 m x 400 micron, finished with 12 mm cement plaster 1:3 (1 cement : 3 coarse sand) and a coat of neat cement, rounding the edges and making and finishing the outlet complete

Item number
12.22
Analysis basis
10 nos
Priced inputs
23
Derived rate
₹298.25/ NO
D-01/RATE ANALYSISITEM 12.22

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.22 (Making khurras 45x45 cm with average minimum thickness of 5 cm cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 20 mm nominal size) over P.V.C. sheet 1 m x1 m x 400 micron, finished with 12 mm cement plaster 1:3 (1 cement : 3 coarse sand) and a coat of neat cement, rounding the edges and making and finishing the outlet complete) is derived from 23 priced inputs for 10 nos and works out to ₹298.25 per no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
ANALYSIS OF RATES · ITEM 12.22DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum0.0671,425.0095.48
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.0221,400.0030.80
0982MATCoarse sand (zone III)cum0.0441,450.0063.80
0367MATPortland Cement (OPC-43 grade)tonne0.0325,156.00164.99
0114LABBeldarday0.09736.0066.24
0115LABCoolieday0.06736.0044.16
0101LABBhistiday0.027816.0022.03
0123LABMason 1st classMason 1st classday0.005897.004.49
0124LABMason 2nd classMason 2nd classday0.005816.004.08
0128LABMateday0.004816.003.26
9999MATHire and running charge of mechanical mixerL.S.2.62.275.90
9999MATSundriesL.S.1.32.272.95
3002MATPolyvinyle chloride sheet 400 micron thickPolyvinyl chloride sheet 400 micron thicksqm1047.00470.00
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum0.0414,881.95200.16
0155LABMason (average)day0.235857.00201.40
0115LABCoolieday0.235736.00172.96
0101LABBhistiday0.078816.0063.65
9999MATSundriesL.S.3.92.278.85
0367MATPortland Cement (OPC-43 grade)tonne0.0065,156.0030.94
0155LABMason (average)day0.08857.0068.56
0115LABCoolieday0.08736.0058.88
9999MATRounding of edges and making outletL.S.2.62.275.90
9999MATSundriesL.S.135.22.27306.90
BUILD-UP TO RATE
TOTAL
2,096.38
Add 1 % Water charges on “W”
+20.96
TOTAL
2,117.34
Add GST on “X” (multiplying factor 0.2127)
+450.36
TOTAL
2,567.70
Add 15% CPOH on “Y”
+385.16
TOTAL
2,952.86
Add Cess @ 1% on “Z”
+29.53
Cost of 10 nos.
2,982.39
Cost of 1 no.
298.24
SAY
₹298.25
D-02/SOURCEPRINTED PAGE 878
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
878

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 878. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.