CPWD Analysis of Rates · Roofing

Providing and laying brick tiles over mumty roofs, grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement, over 12 mm layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished neat

With common burnt clay F.P.S. (non modular) brick tiles of class designation 10

Item number
12.19.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
7
Derived rate
607.40 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.19.1 Providing and laying brick tiles over mumty roofs, grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement, over 12 mm layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished neat: With common burnt clay F.P.S. (non modular) brick tiles of class designation 10 — is derived from 7 priced inputs for 10 sqm and works out to ₹607.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Integral water proofing compound 2% by
  • weight of cement
CodeInputUnitQuantityRate (INR)Amount (INR)
1984Common burnt clay F.P.S. (non modular) bricks tile class designation 10Common burnt clay F.P.S. bricks tile class designation 10Material1000 Nos0.384,750.001,805.00
Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3Sub-analysiscum0.1794,379.05783.85
1213Water proofing materialsMaterialkilogram0.00545.000.23
0124Mason 2nd classMason 2nd classLabourday0.81816.00660.96
0115CoolieLabourday1.08736.00794.88
0101BhistiLabourday0.27816.00220.32
9999SundriesMaterialL.S.1.822.274.13
TOTAL
4,269.37
Add 1 % Water charges on “W”
42.69
TOTAL
4,312.06
Add GST on “X” (multiplying factor 0.2127)
917.18
TOTAL
5,229.24
Add 15% CPOH on “Y”
784.39
TOTAL
6,013.63
Add Cess @ 1% on “Z”
60.14
Cost of 10.00 sqm.
6,073.77
Cost of 1 Sqm.
607.38
Say
607.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 876. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.