CPWD Analysis of Rates · Roofing

Extra for every additional 1 cm thickness of mud phaska

Item number
12.18
Analysis basis
Detail of cost for 10 sqm
Priced inputs
4
Derived rate
24.20 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.18 Extra for every additional 1 cm thickness of mud phaska — is derived from 4 priced inputs for 10 sqm and works out to ₹24.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • For 10 cm thickness
  • Mud Phuska = 1.048 cum. +
  • Wastage 20% = 0.209
  • = 1.257 cum.
  • Quantity for 1 cm thickness 1.257/10 =
  • 0.1257 cum say 0.13 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
0811Mud (dry)Materialcum0.13190.0024.70
0114BeldarLabourday0.07736.0051.52
0101BhistiLabourday0.04816.0032.64
9999Labour for leaping and carring to roofMaterialL.S.26.912.2761.09
TOTAL
169.95
Add 1 % Water charges on “W”
1.70
TOTAL
171.65
Add GST on “X” (multiplying factor 0.2127)
36.51
TOTAL
208.16
Add 15% CPOH on “Y”
31.22
TOTAL
239.38
Add Cess @ 1% on “Z”
2.39
Cost of 10.00 sqm.
241.77
Cost of 1 Sqm.
24.18
Say
24.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 876. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.