R/DAR 2023

10cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar with bhusha @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow-dung) and covered with machine moulded tile bricks, grouted with cement mortar 1:3 ( 1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat

With machine moulded common burnt clay F.P.S. (non modular) brick tiles of class designation 12.5, conforming to IS 2690
Item number
12.17.1
Analysis basis
Details of cost for (mud) 10.00sqm.
Priced inputs
13
Derived rate
₹1,074.50/ SQM
D-01/RATE ANALYSISITEM 12.17.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.17.1 (10cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar with bhusha @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow-dung) and covered with machine moulded tile bricks, grouted with cement mortar 1:3 ( 1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat With machine moulded common burnt clay F.P.S. (non modular) brick tiles of class designation 12.5, conforming to IS 2690) is derived from 13 priced inputs and works out to ₹1,074.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Mud Phuska = 1.048 cum.
  • Wastage 20% = 0.209
  • Total = 1.257 cum.
  • Mud mortar for 25 mm thick plaster over
  • phuska
  • Bhusa 0.263x35 = 9.20
  • 5% wastage = 0.46
  • Total = 9.66 Kg. say 10 kg = 0.1 q
  • Integral water proofing compound 2% by
  • weight of cement
ANALYSIS OF RATES · ITEM 12.17.1DETAILS OF COST FOR (MUD) 10.00SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0811MATMud (dry)cum1.257190.00238.83
SUBRate as per Item Number 3.18 of SH: MortarsRate as per item 3.18cum0.263940.55247.36
0308MATBhusaquintal0.1530.0053.00
9999MATCowdungL.S.5.332.2712.10
9999MATMud mortar for gobri leapingL.S.8.062.2718.30
9977MATCarriage of bhusa and cowdungL.S.2.732.276.20
7904MATMachine moulded common burnt clay tile bricks of class designation 12.51000 Nos0.385,200.001,976.00
SUBRate as per Item Number 3.3 of SH: MortarsRate as per item 3.3cum0.0614,379.05267.12
1213MATWater proofing materialskilogram0.00645.000.27
9999MATSundriesL.S.6.762.2715.35
0124LABMason 2nd classMason 2nd classday1.3816.001,060.80
0114LABBeldarday3.75736.002,760.00
0101LABBhistiday1.1816.00897.60
BUILD-UP TO RATE
TOTAL
7,552.93
Add 1 % Water charges on “W”
+75.53
TOTAL
7,628.46
Add GST on “X” (multiplying factor 0.2127)
+1,622.57
TOTAL
9,251.03
Add 15% CPOH on “Y”
+1,387.65
TOTAL
10,638.68
Add Cess @ 1% on “Z”
+106.39
Cost of 10.00 sqm.
10,745.07
Cost of 1 Sqm.
1,074.51
SAY
₹1,074.50
D-02/SOURCEPRINTED PAGE 875
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
875

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 875. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.