CPWD Analysis of Rates · Roofing
10cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar with bhusha @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow-dung) and covered with machine moulded tile bricks, grouted with cement mortar 1:3 ( 1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat
With machine moulded common burnt clay F.P.S. (non modular) brick tiles of class designation 12.5, conforming to IS 2690
- Item number
- 12.17.1
- Analysis basis
- Details of cost for (mud) 10.00sqm.
- Priced inputs
- 13
- Derived rate
- ₹1,074.50 / Sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.17.1 — 10cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar with bhusha @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow-dung) and covered with machine moulded tile bricks, grouted with cement mortar 1:3 ( 1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat With machine moulded common burnt clay F.P.S. (non modular) brick tiles of class designation 12.5, conforming to IS 2690 — is derived from 13 priced inputs and works out to ₹1,074.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Mud Phuska = 1.048 cum.
- Wastage 20% = 0.209
- Total = 1.257 cum.
- Mud mortar for 25 mm thick plaster over
- phuska
- Bhusa 0.263x35 = 9.20
- 5% wastage = 0.46
- Total = 9.66 Kg. say 10 kg = 0.1 q
- Integral water proofing compound 2% by
- weight of cement
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0811 | Mud (dry)Material | cum | 1.257 | 190.00 | 238.83 |
| Rate as per Item Number 3.18 of SH: MortarsRate as per item 3.18Sub-analysis | cum | 0.263 | 940.55 | 247.36 | |
| 0308 | BhusaMaterial | quintal | 0.1 | 530.00 | 53.00 |
| 9999 | CowdungMaterial | L.S. | 5.33 | 2.27 | 12.10 |
| 9999 | Mud mortar for gobri leapingMaterial | L.S. | 8.06 | 2.27 | 18.30 |
| 9977 | Carriage of bhusa and cowdungMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 7904 | Machine moulded common burnt clay tile bricks of class designation 12.5Material | 1000 Nos | 0.38 | 5,200.00 | 1,976.00 |
| Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3Sub-analysis | cum | 0.061 | 4,379.05 | 267.12 | |
| 1213 | Water proofing materialsMaterial | kilogram | 0.006 | 45.00 | 0.27 |
| 9999 | SundriesMaterial | L.S. | 6.76 | 2.27 | 15.35 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 1.3 | 816.00 | 1,060.80 |
| 0114 | BeldarLabour | day | 3.75 | 736.00 | 2,760.00 |
| 0101 | BhistiLabour | day | 1.1 | 816.00 | 897.60 |
- TOTAL
- 7,552.93
- Add 1 % Water charges on “W”
- 75.53
- TOTAL
- 7,628.46
- Add GST on “X” (multiplying factor 0.2127)
- 1,622.57
- TOTAL
- 9,251.03
- Add 15% CPOH on “Y”
- 1,387.65
- TOTAL
- 10,638.68
- Add Cess @ 1% on “Z”
- 106.39
- Cost of 10.00 sqm.
- 10,745.07
- Cost of 1 Sqm.
- 1,074.51
- Say
- 1,074.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 875. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.