CPWD Analysis of Rates · Roofing
10 cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar mixed with bhusa @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow dung) and covered with flat tile bricks, grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat
With common burnt clay F.P.S.(non modular) brick tile of class designation 10
- Item number
- 12.16.1
- Analysis basis
- Details of cost for (mud phaska) 10.00sqm.
- Priced inputs
- 13
- Derived rate
- ₹1,050.20 / Sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.16.1 — 10 cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar mixed with bhusa @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow dung) and covered with flat tile bricks, grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat: With common burnt clay F.P.S.(non modular) brick tile of class designation 10 — is derived from 13 priced inputs and works out to ₹1,050.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Mud Phuska = 1.048 cum. +
- Wastage 20% = 0.209 = 1.257 cum.
- Mud mortar for 25 mm thick plaster over
- phuska
- Bhusa 0.263x35 = 9.20 +
- 5% wastage = 0.46
- Total = 9.66 Kg. say 10 kg = 0.1 q
- Tile bricks 22.9x11.4x4.4cm of designation
- 100
- Integral water proofing compound 2% by
- weight of cement
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0811 | Mud (dry)Material | cum | 1.257 | 190.00 | 238.83 |
| Rate as per Item Number 3.18 of SH: MortarsRate as per item 3.18Sub-analysis | cum | 0.263 | 940.55 | 247.36 | |
| 0308 | BhusaMaterial | quintal | 0.1 | 530.00 | 53.00 |
| 9999 | CowdungMaterial | L.S. | 5.33 | 2.27 | 12.10 |
| 9999 | Mud mortar for gobri leapingMaterial | L.S. | 8.06 | 2.27 | 18.30 |
| 9977 | Carriage of bhusa and cowdungMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 1984 | Common burnt clay F.P.S. (non modular) bricks tile class designation 10Common burnt clay F.P.S. bricks tile class designation 10Material | 1000 Nos | 0.38 | 4,750.00 | 1,805.00 |
| Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3Sub-analysis | cum | 0.061 | 4,379.05 | 267.12 | |
| 1213 | Water proofing materialsMaterial | kilogram | 0.006 | 45.00 | 0.27 |
| 9999 | SundriesMaterial | L.S. | 6.76 | 2.27 | 15.35 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 1.3 | 816.00 | 1,060.80 |
| 0114 | BeldarLabour | day | 3.75 | 736.00 | 2,760.00 |
| 0101 | BhistiLabour | day | 1.1 | 816.00 | 897.60 |
- TOTAL
- 7,381.93
- Add 1 % Water charges on “W”
- 73.82
- TOTAL
- 7,455.75
- Add GST on “X” (multiplying factor 0.2127)
- 1,585.84
- TOTAL
- 9,041.59
- Add 15% CPOH on “Y”
- 1,356.24
- TOTAL
- 10,397.83
- Add Cess @ 1% on “Z”
- 103.98
- Cost of 10.00 sqm.
- 10,501.81
- Cost of 1 Sqm.
- 1,050.18
- Say
- 1,050.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 874. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.