CPWD Analysis of Rates · Roofing
Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete
S type louvers
- Item number
- 12.13.8
- Analysis basis
- Details of cost for 8.74 metres
- Priced inputs
- 11
- Derived rate
- ₹560.05 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.8 — Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: S type louvers — is derived from 11 priced inputs for 8.74 metres and works out to ₹560.05 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- S type louvers = 5 nos.+
- Total = 5.25 nos.
- Add 5% wastage = 0.25 nos.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0235 | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement S type louversMaterial | each | 5.25 | 280.00 | 1,470.00 |
| 9977 | CarriageMaterial | L.S. | 10.79 | 2.27 | 24.49 |
| 1031 | Galvanised steel bolts & nuts 10 mm dia and 27 cm long both sides threaded with4 galvanised steel nutsGalvanised steel bolts & nuts 10 mm dia and 27 cm long both sides threaded with 4 galvanised steel nutsMaterial | each | 6 | 20.00 | 120.00 |
| 1032 | Galvanised steel bolts 10 mm dia and 7 cm long with nutsMaterial | each | 6 | 6.00 | 36.00 |
| 1208 | Bitumen washerMaterial | 100 Nos | 0.18 | 30.00 | 5.40 |
| 1210 | G.I. plain washer thinMaterial | 100 Nos | 0.36 | 21.00 | 7.56 |
| 9977 | Carriage of bolts and nuts and washersMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | SundriesMaterial | L.S. | 13.39 | 2.27 | 30.40 |
| 0111 | Carpenter 1st classLabour | day | 1 | 897.00 | 897.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 0102 | Blacksmith 1st classLabour | day | 0.12 | 897.00 | 107.64 |
- TOTAL
- 3,440.69
- Add 1 % Water charges on “W”
- 34.41
- TOTAL
- 3,475.10
- Add GST on “X” (multiplying factor 0.2127)
- 739.15
- TOTAL
- 4,214.25
- Add 15% CPOH on “Y”
- 632.14
- TOTAL
- 4,846.39
- Add Cess @ 1% on “Z”
- 48.46
- Cost of 8.74 metres
- 4,894.85
- Cost of 1.00 metre
- 560.05
- Say
- 560.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 872. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.