CPWD Analysis of Rates · Roofing

Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete

S type louvers

Item number
12.13.8
Analysis basis
Details of cost for 8.74 metres
Priced inputs
11
Derived rate
560.05 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.8 Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: S type louvers — is derived from 11 priced inputs for 8.74 metres and works out to ₹560.05 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • S type louvers = 5 nos.+
  • Total = 5.25 nos.
  • Add 5% wastage = 0.25 nos.
CodeInputUnitQuantityRate (INR)Amount (INR)
0235Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement S type louversMaterialeach5.25280.001,470.00
9977CarriageMaterialL.S.10.792.2724.49
1031Galvanised steel bolts & nuts 10 mm dia and 27 cm long both sides threaded with4 galvanised steel nutsGalvanised steel bolts & nuts 10 mm dia and 27 cm long both sides threaded with 4 galvanised steel nutsMaterialeach620.00120.00
1032Galvanised steel bolts 10 mm dia and 7 cm long with nutsMaterialeach66.0036.00
1208Bitumen washerMaterial100 Nos0.1830.005.40
1210G.I. plain washer thinMaterial100 Nos0.3621.007.56
9977Carriage of bolts and nuts and washersMaterialL.S.2.732.276.20
9999SundriesMaterialL.S.13.392.2730.40
0111Carpenter 1st classLabourday1897.00897.00
0114BeldarLabourday1736.00736.00
0102Blacksmith 1st classLabourday0.12897.00107.64
TOTAL
3,440.69
Add 1 % Water charges on “W”
34.41
TOTAL
3,475.10
Add GST on “X” (multiplying factor 0.2127)
739.15
TOTAL
4,214.25
Add 15% CPOH on “Y”
632.14
TOTAL
4,846.39
Add Cess @ 1% on “Z”
48.46
Cost of 8.74 metres
4,894.85
Cost of 1.00 metre
560.05
Say
560.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 872. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.