Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete
- Item number
- 12.13.7
- Analysis basis
- 20 Nos
- Priced inputs
- 9
- Derived rate
- ₹1,013.85/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.7 (Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: Special north light curves) is derived from 9 priced inputs for 20 Nos and works out to ₹1,013.85 per no after water charges, GST, CPOH and cess. The full build-up is below.
- Details of special north light ventilator curve
- 20.2 metres long complete length
- Special north light curves of 1.016 metres
- nominal length = 20 nos. +
- Total = 21 nos.
- Add 5% wastage = 1.0 No.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0234 | MAT | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement special north light curves | each | 21 | 600.00 | 12,600.00 |
| 1023 | MAT | Galvanised steel J or L hooks 8 mm dia | 10 Nos | 4 | 130.00 | 520.00 |
| 1209 | MAT | G.I. plain washer thick | 100 Nos | 0.4 | 35.00 | 14.00 |
| 1208 | MAT | Bitumen washer | 100 Nos | 0.4 | 30.00 | 12.00 |
| 9977 | MAT | Carriage of hooks, nuts, washers and curves | L.S. | 9.88 | 2.27 | 22.43 |
| 9999 | MAT | Sundries | L.S. | 6.24 | 2.27 | 14.16 |
| 0130 | LAB | Mistry | day | 0.1 | 897.00 | 89.70 |
| 0112 | LAB | Carpenter 2nd class | day | 0.3 | 816.00 | 244.80 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
- TOTAL
- 14,253.09
- Add 1 % Water charges on “W”
- +142.53
- TOTAL
- 14,395.62
- Add GST on “X” (multiplying factor 0.2127)
- +3,061.95
- TOTAL
- 17,457.57
- Add 15% CPOH on “Y”
- +2,618.64
- TOTAL
- 20,076.21
- Add Cess @ 1% on “Z”
- +200.76
- Cost of 20 nos
- 20,276.97
- Cost of 1.00 no
- 1,013.85
- SAY
- ₹1,013.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 871
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 871. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.