CPWD Analysis of Rates · Roofing
Providing flat iron brackets 50x3 mm size with necessary bolts, nuts and washers etc. for fixing G.S. sheets gutters with purlins
- Item number
- 12.14
- Analysis basis
- Detail of cost for 200 metre
- Priced inputs
- 6
- Derived rate
- ₹92.40 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.14 — Providing flat iron brackets 50x3 mm size with necessary bolts, nuts and washers etc. for fixing G.S. sheets gutters with purlins — is derived from 6 priced inputs for 200 metre and works out to ₹92.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Flat 50x3mm size
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1008 | Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterial | quintal | 1.163 | 5,450.00 | 6,338.35 |
| 1025 | Mild stel bolts 6 mm dia and 25 mm long with hexagonal headMild steel bolts 6 mm dia and 25 mm long with hexagonal headMaterial | 10 Nos | 38 | 10.00 | 380.00 |
| 1210 | G.I. plain washer thinMaterial | 100 Nos | 1.9 | 21.00 | 39.90 |
| 9999 | SundriesMaterial | L.S. | 10.4 | 2.27 | 23.61 |
| 0102 | Blacksmith 1st classLabour | day | 3.8 | 897.00 | 3,408.60 |
| 0114 | BeldarLabour | day | 3.8 | 736.00 | 2,796.80 |
- TOTAL
- 12,987.26
- Add 1 % Water charges on “W”
- 129.87
- TOTAL
- 13,117.13
- Add GST on “X” (multiplying factor 0.2127)
- 2,790.01
- TOTAL
- 15,907.14
- Add 15% CPOH on “Y”
- 2,386.07
- TOTAL
- 18,293.21
- Add Cess @ 1% on “Z”
- 182.93
- Cost of 200 metre
- 18,476.14
- Cost of 1.00 metre
- 92.38
- Say
- 92.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 872. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.