Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete
- Item number
- 12.13.5
- Analysis basis
- 9.70 metres
- Priced inputs
- 9
- Derived rate
- ₹724.65/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.5 (Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: Barge boards) is derived from 9 priced inputs for 9.70 metres and works out to ₹724.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Completed length of barge boards
- Barge boards 2.50metres = 4 nos. x 2.50 =
- 10.00 metre
- Total = 10.50 metre.
- Add 5% wastage = 0.50 metre.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0232 | MAT | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement barge boards 6 mm thickFibre reinforced by organic fibres and/or inorganic synthetic fibres cement barge boards boards 6 mm thick | metre | 10.5 | 430.00 | 4,515.00 |
| 0222 | MAT | Seam bolts and nuts 6 mm dia and 25 mm long | 10 Nos | 0.5 | 11.00 | 5.50 |
| 1211 | MAT | G.I. plain washer for seam bolts | 100 Nos | 0.1 | 32.00 | 3.20 |
| 1208 | MAT | Bitumen washer | 100 Nos | 0.05 | 30.00 | 1.50 |
| 9977 | MAT | Carriage of barge boards, bolts, nuts and washers | L.S. | 9.36 | 2.27 | 21.25 |
| 9999 | MAT | Sundries | L.S. | 6.76 | 2.27 | 15.35 |
| 0130 | LAB | Mistry | day | 0.04 | 897.00 | 35.88 |
| 0112 | LAB | Carpenter 2nd class | day | 0.06 | 816.00 | 48.96 |
| 0114 | LAB | Beldar | day | 0.4 | 736.00 | 294.40 |
- TOTAL
- 4,941.04
- Add 1 % Water charges on “W”
- +49.41
- TOTAL
- 4,990.45
- Add GST on “X” (multiplying factor 0.2127)
- +1,061.47
- TOTAL
- 6,051.92
- Add 15% CPOH on “Y”
- +907.79
- TOTAL
- 6,959.71
- Add Cess @ 1% on “Z”
- +69.60
- Cost of 9.70 metre
- 7,029.31
- Cost of 1.00 metre
- 724.67
- SAY
- ₹724.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 870
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 870. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.