Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete

Barge boards
Item number
12.13.5
Analysis basis
9.70 metres
Priced inputs
9
Derived rate
₹724.65/ METRE
D-01/RATE ANALYSISITEM 12.13.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.5 (Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: Barge boards) is derived from 9 priced inputs for 9.70 metres and works out to ₹724.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Completed length of barge boards
  • Barge boards 2.50metres = 4 nos. x 2.50 =
  • 10.00 metre
  • Total = 10.50 metre.
  • Add 5% wastage = 0.50 metre.
ANALYSIS OF RATES · ITEM 12.13.5DETAILS OF COST FOR 9.70 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0232MATFibre reinforced by organic fibres and/or inorganic synthetic fibres cement barge boards 6 mm thickFibre reinforced by organic fibres and/or inorganic synthetic fibres cement barge boards boards 6 mm thickmetre10.5430.004,515.00
0222MATSeam bolts and nuts 6 mm dia and 25 mm long10 Nos0.511.005.50
1211MATG.I. plain washer for seam bolts100 Nos0.132.003.20
1208MATBitumen washer100 Nos0.0530.001.50
9977MATCarriage of barge boards, bolts, nuts and washersL.S.9.362.2721.25
9999MATSundriesL.S.6.762.2715.35
0130LABMistryday0.04897.0035.88
0112LABCarpenter 2nd classday0.06816.0048.96
0114LABBeldarday0.4736.00294.40
BUILD-UP TO RATE
TOTAL
4,941.04
Add 1 % Water charges on “W”
+49.41
TOTAL
4,990.45
Add GST on “X” (multiplying factor 0.2127)
+1,061.47
TOTAL
6,051.92
Add 15% CPOH on “Y”
+907.79
TOTAL
6,959.71
Add Cess @ 1% on “Z”
+69.60
Cost of 9.70 metre
7,029.31
Cost of 1.00 metre
724.67
SAY
₹724.65
D-02/SOURCEPRINTED PAGE 870
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
870

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 870. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.