Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete

Ventilator curves
Item number
12.13.4
Priced inputs
9
Derived rate
₹627.30/ METRE
D-01/RATE ANALYSISITEM 12.13.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.4 (Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: Ventilator curves) is derived from 9 priced inputs and works out to ₹627.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Details of ventilator curve 20.2 metres long
  • complete length
  • Ventilator curves of 1.016 metres nominal
  • length = 20 nos. +
  • Total = 21 nos.x 1.016 = 21.336 metre
  • Add 5% wastage = 1.0 No.
ANALYSIS OF RATES · ITEM 12.13.4
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0231MATFibre reinforced by organic fibres and/or inorganic synthetic fibres cement ventilator curveseach21.336340.007,254.24
1023MATGalvanised steel J or L hooks 8 mm dia10 Nos4130.00520.00
1209MATG.I. plain washer thick100 Nos0.435.0014.00
1208MATBitumen washer100 Nos0.430.0012.00
9977MATCarriage of hooks, nuts, washers and curvesL.S.9.882.2722.43
9999MATSundriesL.S.6.242.2714.16
0130LABMistryday0.1897.0089.70
0112LABCarpenter 2nd classday0.3816.00244.80
0114LABBeldarday1736.00736.00
BUILD-UP TO RATE
TOTAL
8,907.33
Add 1 % Water charges on “W”
+89.07
TOTAL
8,996.40
Add GST on “X” (multiplying factor 0.2127)
+1,913.53
TOTAL
10,909.93
Add 15% CPOH on “Y”
+1,636.49
TOTAL
12,546.42
Add Cess @ 1% on “Z”
+125.46
Cost of 20.20 metre
12,671.88
Cost of 1.00 metre
627.32
SAY
₹627.30
D-02/SOURCEPRINTED PAGE 869
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
869

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 869. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.