CPWD Analysis of Rates · Roofing

Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete

Ventilator curves

Item number
12.13.4
Priced inputs
9
Derived rate
627.30 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.4 Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: Ventilator curves — is derived from 9 priced inputs and works out to ₹627.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Details of ventilator curve 20.2 metres long
  • complete length
  • Ventilator curves of 1.016 metres nominal
  • length = 20 nos. +
  • Total = 21 nos.x 1.016 = 21.336 metre
  • Add 5% wastage = 1.0 No.
CodeInputUnitQuantityRate (INR)Amount (INR)
0231Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement ventilator curvesMaterialeach21.336340.007,254.24
1023Galvanised steel J or L hooks 8 mm diaMaterial10 Nos4130.00520.00
1209G.I. plain washer thickMaterial100 Nos0.435.0014.00
1208Bitumen washerMaterial100 Nos0.430.0012.00
9977Carriage of hooks, nuts, washers and curvesMaterialL.S.9.882.2722.43
9999SundriesMaterialL.S.6.242.2714.16
0130MistryLabourday0.1897.0089.70
0112Carpenter 2nd classLabourday0.3816.00244.80
0114BeldarLabourday1736.00736.00
TOTAL
8,907.33
Add 1 % Water charges on “W”
89.07
TOTAL
8,996.40
Add GST on “X” (multiplying factor 0.2127)
1,913.53
TOTAL
10,909.93
Add 15% CPOH on “Y”
1,636.49
TOTAL
12,546.42
Add Cess @ 1% on “Z”
125.46
Cost of 20.20 metre
12,671.88
Cost of 1.00 metre
627.32
Say
627.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 869. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.