CPWD Analysis of Rates · Roofing

Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete

Corrugated apron pieces

Item number
12.13.1
Priced inputs
6
Derived rate
428.50 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.1 Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: Corrugated apron pieces — is derived from 6 priced inputs and works out to ₹428.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Details for shed of 20.2 metres completed
  • length
  • Corrugated appron pieces of 1.12 metre
  • length = 20 nos.+
  • Total = 21 nos.x 1.12=23.52 metre
  • Add 5% wastage = 1.0 No.
CodeInputUnitQuantityRate (INR)Amount (INR)
0228Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated appron pieceFibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated apron pieceMaterialmetre23.52220.005,174.40
9977Carriage of appron pieces. (The appron pieces are to be fixed with the same hooks as the sheets)MaterialL.S.3.252.277.38
9999SundriesMaterialL.S.3.252.277.38
0130MistryLabourday0.07897.0062.79
0112Carpenter 2nd classLabourday0.28816.00228.48
0114BeldarLabourday0.82736.00603.52
TOTAL
6,083.95
Add 1 % Water charges on “W”
60.84
TOTAL
6,144.79
Add GST on “X” (multiplying factor 0.2127)
1,307.00
TOTAL
7,451.79
Add 15% CPOH on “Y”
1,117.77
TOTAL
8,569.56
Add Cess @ 1% on “Z”
85.70
Cost of 20.20 metre
8,655.26
Cost of 1.00 metre
428.48
Say
428.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 867. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.