Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete
- Item number
- 12.13.1
- Priced inputs
- 6
- Derived rate
- ₹428.50/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.1 (Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: Corrugated apron pieces) is derived from 6 priced inputs and works out to ₹428.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Details for shed of 20.2 metres completed
- length
- Corrugated appron pieces of 1.12 metre
- length = 20 nos.+
- Total = 21 nos.x 1.12=23.52 metre
- Add 5% wastage = 1.0 No.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0228 | MAT | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated appron pieceFibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated apron piece | metre | 23.52 | 220.00 | 5,174.40 |
| 9977 | MAT | Carriage of appron pieces. (The appron pieces are to be fixed with the same hooks as the sheets) | L.S. | 3.25 | 2.27 | 7.38 |
| 9999 | MAT | Sundries | L.S. | 3.25 | 2.27 | 7.38 |
| 0130 | LAB | Mistry | day | 0.07 | 897.00 | 62.79 |
| 0112 | LAB | Carpenter 2nd class | day | 0.28 | 816.00 | 228.48 |
| 0114 | LAB | Beldar | day | 0.82 | 736.00 | 603.52 |
- TOTAL
- 6,083.95
- Add 1 % Water charges on “W”
- +60.84
- TOTAL
- 6,144.79
- Add GST on “X” (multiplying factor 0.2127)
- +1,307.00
- TOTAL
- 7,451.79
- Add 15% CPOH on “Y”
- +1,117.77
- TOTAL
- 8,569.56
- Add Cess @ 1% on “Z”
- +85.70
- Cost of 20.20 metre
- 8,655.26
- Cost of 1.00 metre
- 428.48
- SAY
- ₹428.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 867
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 867. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.