Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete

Corrugated apron pieces
Item number
12.13.1
Priced inputs
6
Derived rate
₹428.50/ METRE
D-01/RATE ANALYSISITEM 12.13.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.1 (Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: Corrugated apron pieces) is derived from 6 priced inputs and works out to ₹428.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Details for shed of 20.2 metres completed
  • length
  • Corrugated appron pieces of 1.12 metre
  • length = 20 nos.+
  • Total = 21 nos.x 1.12=23.52 metre
  • Add 5% wastage = 1.0 No.
ANALYSIS OF RATES · ITEM 12.13.1
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0228MATFibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated appron pieceFibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated apron piecemetre23.52220.005,174.40
9977MATCarriage of appron pieces. (The appron pieces are to be fixed with the same hooks as the sheets)L.S.3.252.277.38
9999MATSundriesL.S.3.252.277.38
0130LABMistryday0.07897.0062.79
0112LABCarpenter 2nd classday0.28816.00228.48
0114LABBeldarday0.82736.00603.52
BUILD-UP TO RATE
TOTAL
6,083.95
Add 1 % Water charges on “W”
+60.84
TOTAL
6,144.79
Add GST on “X” (multiplying factor 0.2127)
+1,307.00
TOTAL
7,451.79
Add 15% CPOH on “Y”
+1,117.77
TOTAL
8,569.56
Add Cess @ 1% on “Z”
+85.70
Cost of 20.20 metre
8,655.26
Cost of 1.00 metre
428.48
SAY
₹428.50
D-02/SOURCEPRINTED PAGE 867
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
867

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 867. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.