CPWD Analysis of Rates · Roofing
Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete
Unserrated adjustable hips
- Item number
- 12.12.4
- Analysis basis
- Details of cost for a shed with hip as 20.2
- Priced inputs
- 6
- Derived rate
- ₹521.85 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.12.4 — Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete Unserrated adjustable hips — is derived from 6 priced inputs for a shed and works out to ₹521.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- metres Unserrated adjustable hips
- Consider a shed with hip as 20.2 metres
- No. of hi pieces required = 19 pairs
- Length of each pair 1.22 metres
- = 19.95 pairs x 1.22 = 24.339 metre
- Add 5 % wastage = 0.95 pairs
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0227 | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement unserrated adjustable ridge for hipsFibre (high impact poly propelene reinforced) cement unserrated adjustable ridge for hipsMaterial | metre | 24.339 | 230.00 | 5,597.97 |
| 9977 | CarriageMaterial | L.S. | 6.76 | 2.27 | 15.35 |
| 9999 | SundriesMaterial | L.S. | 6.63 | 2.27 | 15.05 |
| 0130 | MistryLabour | day | 0.14 | 897.00 | 125.58 |
| 0112 | Carpenter 2nd classLabour | day | 0.55 | 816.00 | 448.80 |
| 0114 | BeldarLabour | day | 1.64 | 736.00 | 1,207.04 |
- TOTAL
- 7,409.79
- Add 1 % Water charges on “W”
- 74.10
- TOTAL
- 7,483.89
- Add GST on “X” (multiplying factor 0.2127)
- 1,591.82
- TOTAL
- 9,075.71
- Add 15% CPOH on “Y”
- 1,361.36
- TOTAL
- 10,437.07
- Add Cess @ 1% on “Z”
- 104.37
- Cost of 20.20 metre
- 10,541.44
- Cost of 1.00 metre
- 521.85
- Say
- 521.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 867. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works